HomeMy WebLinkAboutRES 10-304 RESOLUTION NO.10-304
WHEREAS, on June 29, 2010, the City Council of the City of Beaumont, Texas,
passed Resolution No. 10-174 awarding a contract in the amount of$3,844,851.18 to C.
F. Jordan Construction, L.L.C., for the Event Center Area Paving and Drainage
Improvements Project; and,
WHEREAS, Change Order No. 1 in the amount of$156,279.43 is required to install
new water mains and appurtenances, thereby increasing the contract amount to
$4,001,130.61; and,
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 1 in the amount of 156,279.43, thereby increasing the contract amount to
$4,001,130.61.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 16th day of
November, 2010.
rIA
- ayor Becky Ames -
l�
CITY OF BEAUMONT
DATE: 29 October 2010
PROJECT: EVENT CENTER AREA PAVING AND DRAINAGE IMPROVEMENTS
OWNER: CITY OF BEAUMONT
CONTRACTOR: CF JORDAN CONSTRUCTION CONSTRUCTION L.L.C.
CHANGE ORDER NO.: 01
??':
..........................::..........................................:.....................:........................................:.:.::::. ::.:::::::.........:........:::::.::::::.::.::::.:
:::::::...........................::::::..
Add Construction Items and/or quantities to the Contract:
Item Item Original New Unit
Description Unit Quantity Amount
No. Code
Q y Quantity Price
WATER UTLITIES
808 9 FURNISH&INSTALL FIRE HYDRANT ASSEMBLY EA 0 4.00 $5,015.00 $20,060.00
810 11 FURNISH&INSTALL 12"CLASS 150-0900 PVC LF 0 3000.00 $39.60 $118,800.00
811 16 FURNISH AND INSTALL 12"TAPPING SLEEVE& EA 0 5.00 $3,295.09 $16,475.44
VALVE
502 101 BARRICADES,SIGNS&TRAFFIC HANDLING MO 24 25.00 $943.99 $943.99
ADD TOTAL AMOUNT $156,279.43
ORIGINAL CONTRACT AMOUNT: $3,844,851.18
NET FROM PREVIOUS CHANGE ORDERS: $0.00
TOTAL AMOUNT OF THIS CHANGE ORDER: $156,279.43
PERCENT OF THIS CHANGE ORDER: 4.06%
TOTAL PERCENT CHANGE ORDER TO DATE: 4.06%
NEW CONTRACT AMOUNT: $4,001,130.61
As
ACCEPTED BY:
ONTRACTOR
APPROVED BY:
PATRICK DONART,CITY HANI TOHME,WATER UTILITIES
ENGINEER DIRECTOR
ATTESTED BY:
Im
A BROUSSARD,CITY CLERK KYLE HAYTN7,CITY MANAGER
AW
Ar