HomeMy WebLinkAboutRES 10-284 RESOLUTION NO.10-284
WHEREAS, on April 28, 2009, the City Council of the City of Beaumont, Texas,
passed Resolution No. 09-117 awarding a contract to R & B Group, Inc., Houston, Texas,
in the amount of$1,296,743.00 for the 23rd Street Lift Station Rehabilitation Project; and,
WHEREAS, Change Order No. 1 in the amount of($11,325.19)was necessary to
construct an 84" reinforced concrete (RC) manhole including RC foundation, RC top slab,
and aluminum hatch in lieu of the proposed junction box and 48" reinforced concrete pipe
(RCP) risers shown on the plans and furnish and install one 30" diameter resilient wedge
gate valve including valve box on the existing 30"diameter force main, thereby decreasing
the contract amount to $1,285,417.81; and
WHEREAS, Change Order No. 2 in the amount of $17,290.95 was necessary to
furnish and install three additional feet of 84-inch riser for the manhole at the proposed
junction box, remove existing flap gate and grout opening on existing drainage box, furnish
and install an additional 810 square feet of six-inch concrete on the west driveway,thereby
increasing the contract time by 10 calendar days and increasing the contract amount to
$1,302,708.76; and,
WHEREAS, Change Order No. 3, dated May 25, 2010, in the amount of$4,118.17
increased the contract amount to $1,306,826.93; and,
WHEREAS,Change Order No.4 in the amount of$13,286.66 is necessary to furnish
modifications to the control systems of the PLC including installation of a horn and alarm
beacon; replacement of the Hydroranger to allow it to operate the pumps in case of the PLC
failure;correct distribution of VFD fail alarm to each pair of pumps by adding a relay to each
VFD; adjustment of cost for installation of the 20 ft. mast and radios at the west elevated
water storage tank; payment for additional fuel usage during the course of the project in
excess of the estimated amount per records from the onsite bypass pumps prior to
commencing the project; payment for additional fuel usage from the time of substantial
completion until the time the City took control of the lift station operation; replacement of two
(2) installed 4" cast iron flap valves with two (2) new 4" PVC flap valves and including a
savings in the amount of $30,000 for the deletion of an allowance for electrical service
installation charges, thereby increasing the total contract time by 30 days and increasing
the contract amount to $1,320,113.59;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
That the City Manager be and he is hereby authorized to execute Change Order No.
4 increasing the contract amount by$13,286.66 for a revised total amount of$1,320,113.59
for the 23`d Street Lift Station Rehabilitation Project.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 2nd day of
November, 2010.