Loading...
HomeMy WebLinkAboutRES 10-047 RESOLUTION NO. 10-047 WHEREAS, on April 28, 2009, the City Council of the City of Beaumont, Texas, passed Resolution No. 09-117 awarding a contract to R & B Group, Inc., Houston, Texas, in the amount of$1,296,743.00 for the 23rd Street Lift Station Rehabilitation Project; and, WHEREAS, Change Order No. 1 in the amount of($11,325.19) was necessary to construct an 84" reinforced concrete (RC) manhole including RC foundation, RC top slab, and aluminum hatch in lieu of the proposed junction box and 48" reinforced concrete pipe (RCP) risers shown on the plans and furnish and install one 30" diameter resilient wedge gate valve including valve box on the existing 30"diameterforce main, thereby decreasing the contract amount to $1,285,417.81; and WHEREAS, Change Order No. 2 in the amount of $17,290.95 is necessary to furnish and install three additional feet of 84-inch riser for the manhole at the proposed junction box, remove existing flap gate and grout opening on existing drainage box,furnish and install an additional 810 square feet of six-inch concrete on the west driveway,thereby increasing the contract time by 10 calendar days and increasing the contract amount to $1,302,708.76. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the City Manager be and he is hereby authorized to execute Change Order No. 2 in the amount of $17,290.95 for extra work described above, thereby increasing the contract amount to $1,302,708.76. PASSED BY THE CIZKQ +I,I�`IL of the City of Beaumont this the 2nd day of I March, 2010. 'r I1 � � yor Becky Ames -