HomeMy WebLinkAboutRES 10-012 RESOLUTION NO. 10-012
WHEREAS, on May 6, 2008, the City Council of the City of Beaumont, Texas,
passed Resolution No. 08-137 awarding a contract in the amount of $8,041,191.50 to
Allco, Ltd., Beaumont, Texas, for a contract for the Proposed Surface Water Treatment
Plant Improvements Phase I Project; and,
WHEREAS, Change Order No. 1 in the amount of $239,066.95 was required to
furnish labor, equipment and material to install a new alum tank, the removal and disposal
of deteriorated existing precast pipe supports, and furnish labor, equipment and material
to install stainless steel pipe supports for each of the three(3)pulsators,thereby increasing
the contract amount to $8,280,258.45; and
WHEREAS, Change Order No. 2 in the amount of $26,195.75 was required to
increase the pulsator concrete and crack repairs in excess of bid quantities in Pulsator#2,
including labor and materials, increasing the contract time by ten (10) days for a total
contract time of 530 calendar days, thereby increasing the contract amount to
$8,306,454.20; and
WHEREAS, Change Order No. 3 in the amount of $209,871.72 was required to
demolish electric manhole duct banks, change PVC conduit to Rigid Galvanized Steel
conduit at Electric Building, remove abandoned 24-inch pipeline, install handrails at
Pulsator raw water channel, provide emergency power for SCADA transmitter, replace (2)
48-inch flow meters with (2) 36-inch flow meters with adaptors for accuracy, upgrade all
windows and doors in Chemical Building to Hurricane rated, install new duct bank from
electric manhole to switch rack, place PatchCrete wainscoat over exposed concrete block
at Chemical Building, install Chemical Building roof drain line to existing catch basin,
I
replace existing 4x4 wooden chlorine ton container runners with 40 lb. steel rail, sample
pump modifications to submersible pumps in lieu of centrifugal pumps, repair leakage and
concrete damage to the walls of the existing Mixed Water Channel, including repair of
through-the-wall cracks with Combiflex, epoxy injection of 562 linear feet of cracks and
sandblasting and coating of the exterior of the channel at Pulsators 1, 2, and 3, replace
trolley hoist for Chemical Building, install electric manhole EMH-7, paint the external
Vacuum Chamber structures for Pulsators 1, 2, and 3, and additional 900 linear feet of 4-
inch electrical PVC electrical installation to Administration Building from electrical
switchgear manhole, increasing the contract time by 115 calendar days for a total contract
time of 648 calendar days and increasing the contract amount to $8,516,325.92; and
WHEREAS, Change Order No.4 in the amount of$200,207.75 is required to furnish
and install stairs and platforms for the new generators,weld monorail joints in the Chlorine
Building, provide concrete paving around the Electrical Building, clean and re-caulk joints
on the 5 MG clearwell cap, install ladders and step platforms in the meter vault, install a
6-inch liner wall at the mixed water channel, replace (2) magna drives at the backwash
pumps, install a 3-inch PVC chlorine solution lines from Chemical Building to the Filter
Building, add PVC expansion joints on wash lines in the Pulsator Basins, pulsator concrete
and crack repairs in excess of bid quantities in Pulsator#3 (including labor and materials),
reconfigure chemical metering pump piping, and upgrade electrical to the Radio Building
and Metal Storage Building, thereby increasing the contract amount to $8,716,533.67.
i
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager is hereby authorized to execute Change Order No. 4 in the
amount of $200,207.75, thereby increasing the contract amount to $8,716,533.67.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 19th day of
January, 2010.
r
r ayor Becky Ames -
w
r. I