HomeMy WebLinkAboutRES 09-330 RESOLUTION NO. 09-330
WHEREAS, on December 11, 2007, the City Council of the City of Beaumont,
Texas, passed Resolution No. 07-402 awarding a contract in the amount of$5,495,820.65
to ALLCO, Inc., for the Rolfe Christopher Pavement Improvement Project (Spur 380-East
Virginia Street, to Hwy 69 S Feeder Road); and,
WHEREAS, Change Order No. 1 in the amount of$195,277.93 was required to add
and increase water and waste water system improvements,thereby increasing the contract
amount to $5,691,098.58; and,
WHEREAS, Change Order No. 2 in the amount of $226,306.93 was required for
widening the roadway pavement of Rolfe Christopher between Florida Avenue and US 69,
96 and 287 Frontage Road,thereby increasing the contract amount to$5,917,405.51;and,
WHEREAS, Change Order No. 3 in the amount of($231,507.83)is required to adjust
estimated construction quantities to match quantities actually used during the performance
of the project, thereby decreasing the contract amount to $5,685,897.68;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order No. 3
in the amount of ($231,507.83), thereby decreasing the contract amount to$5,685,897.68
for the Rolfe Christopher Pavement Improvement Project (Spur 380-East Virginia Street,
to Hwy 69 S Feeder Road).
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to make
final payment in the amount of $284,294.88 to ALLCO, Inc., for the Rolfe Christopher
Pavement Improvement Project(Spur 380-East Virginia Street,to Hwy 69 S Feeder Road).
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 27th day of
October, 2009.
May r ecky Ames -