HomeMy WebLinkAboutRES 09-107 RESOLUTION NO. 09-107
WHEREAS, on October 2, 2007, the City Council of the City of Beaumont, Texas,
passed Resolution No. 07-304 awarding a contract in the amount of$429,796.02 to Allco,
Ltd., Beaumont, Texas, for the Sanitary Sewer Rehabilitation of Small Diameter Mains
Contract - XIII Project; and,
WHEREAS, Change Order No. 1 in the amount of$71,612.80 is required for"extra
work"to rehabilitate approximately 240 linear feet of 6-inch and 1,150 linear feet of 8-inch
sanitary sewer lines, remove and replace four manholes, clean and televise 1,390 linear
feet of existing lines post televise 1,390 linear feet of rehabilitated lines furnish and install
two end of line cleanouts, replace 30 short side service connections and increase the
contract time by 155 calendar days for the area between Fieldwood and Ebonwood Lane
from Edson Drive to Bandera Drive, thereby increasing the contract amount to
$501,408.82.
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager is hereby authorized to execute Change Order No. 1 for
"extra work"described above in the amount of$71,612.80,thereby increasing the contract
amount to $501.408.82.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 21 st day of
April, 2009.
r�I �1
s w - Mayor Becky Ames -
�� i