HomeMy WebLinkAboutRES 09-062 RESOLUTION NO. 09-062 WHEREAS, on May 6, 2008, the City Council of the City of Beaumont, Texas, passed Resolution No. 08-139 awarding a contract in the amount of$1,523,000 plus$1.25 per square foot for soil stabilization to McInnis Construction of Silsbee, Texas, for improvements to Rogers Park; and, WHEREAS, Change Order No. 1, passed by Resolution No. 08-139 on May 6, 2008, to remove 6,905 feet of the walking trail in the amount of ($17,262.50) and for the removal of the resurfacing of the asphalt parking lot on Dowlen Road in the amount of ($40,000) for a total amount of ($57,262.50), thereby decreasing the contract amount to $1,465,737.50; and WHEREAS, Change Order No. 2, passed by Resolution No. 08-232 on August 26, 2008, was required for furnishing and installing additional electrical conduit in the amount of $17,465, said amount to be deducted from a contingency allowance of$30,000,; and WHEREAS, Change Order No. 3 extended the completion time by seventeen (17) days due to Hurricane Ike; and WHEREAS, Change Order No. 4 in the amount of$57,074.60 is required to clean, seal and paint existing tennis court surfaces, install a newfence surrounding existing tennis courts, and remove two concrete tables and replace the existing damaged sidewalk, thereby increasing the contract amount to $1,522,812.10. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the CI Manager be and he is hereby authorized to execute Change Order No. 4 W the amount O $57,074.60 for "e xtr work" described above, thereby increasing the contract amours to $1,522,812.10, fo rimprovements to Roger Par. PASSED BY THE CITY COUNCIL of the City of Beaumont this te24hdayo February, 2009. - U Tem AudWnSamum- ( d\ «. ate s