Loading...
HomeMy WebLinkAboutRES 08-172 RESOLUTION NO. 08-172 WHEREAS, on October 9, 2007, the City Council of the City of Beaumont, Texas, passed Resolution No. 07-327 awarding a contract in the amount of$355,049 to Brystar Contracting of Beaumont, Texas, for the Cathedral Square Brick Paved Sidewalks Construction o Project; and WHEREAS, Change Order No. 1 is necessary due to a decrease in construction item quantities in the amount of ($23,533.66) thereby decreasing the contract amount to $331,515.34; and, WHEREAS, the project has been inspected and completed; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the City Manager be and he is hereby authorized to execute Change Order No. 1 in the amount of ($23,533.66) thereby decreasing the total contract amount $331,515.34 for,the Cathedral Square Brick Paved Sidewalks Construction Project. BE IT FURTHER RESOLVED that the Cathedral Square Brick Paved Sidewalks Construction Project is hereby accepted as complete and the City Manager be, and he is hereby, authorized to issue final payment of$16,575.77 for the completed project. PASSED BY THE CITY COUNCIL of the City of Beaumont this the 3rd day of June, 2008. FF - Mayor Becky Ames - 1 ,.