WHEREAS, on October 24, 2006, the City Council of the City of Beaumont, Texas,
approved Resolution No. 06-325 awarding a contract in the amount of$1,496,254 to Allco,
Ltd., Beaumont,Texas,forthe Rehabilitation of the Wastewater Treatment Facility Primary
and Secondary Trickling Filters; and,
WHEREAS, Change Order No. 1, passed by Resolution No. 07-343 on October 23,
2007, in the amount of $1,377,912.01 was required for "extra work" to remove three
concrete plugs for the headworks building and channel, replace the specified Garlock
gaskets with 1/8" neoprene gaskets on Primary Trickling Filter No. 1, sandblast existing
distribution arms for Primary Trickling Filter No. 2, Secondary Trickling Filter No. 1 and
Secondary Trickling Filter No. 2 to prepare the surfaces to be galvanized, repair three (3)
sections of the distribution tubes from Primary Trickling Filter No. 2 by cutting the bottom
section of the tubes at the weld seams on both sides and installing a 1/4" carbon steel
plate bent to the original radius and cutting new holes for the orifice ports to match the
original holes, furnish and install 325 new stainless steel spreader plates and 325 new
stainless steel spacer plates on Primary Trickling Filter No. 2, repair the top of one
distribution tube section by cutting out the damaged area and welding a 1/4" carbon steel
plate in place and weld up dimple holes on the distribution tubes for Primary Trickling Filter
No. 2, and increase the contract time by 81 calendar days,thereby increasing the contract
amount by $34,965.35 for a total contract amount of $1,531,219.35; and,
WHEREAS, Change Order No. 2 in the amount of$76,485 thereby increasing the
contract amount to $1,607,704.35 is required to furnish labor, equipment and material to
remove the damaged portion of the wall on the final clarifier splitter box, install new
concrete to match the existing wall, reinstall the slide gate brackets, add new plates so that
there is a 1" plate on both sides of the wall, install stainless steel bolts to anchor the slide
gate bracket to the wall and through the plates of the slide gate brackets, and reinstall the
slide gate actuator on the bracket. Replace 430 brass spreader plate assemblies including
spreader plates, spacers, nuts and washers on the existing Secondary Trickling Filter No.
1 with new stainless steel assemblies. Repair 20 distribution tubes on the Secondary
Trickling Filter No. 1 including two (2) 3' by 3' patches, replace the bottom side of one (1)
distribution tube section, and replace the front side of the distribution tubes including
cutting orifice holes for the spreader plate assemblies
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order No. 2
for "extra work" as described above, thereby increasing the contract amount by $76,485
for a total contract amount of$1,607,704.35.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 15th day of
January, 2008.