HomeMy WebLinkAboutRES 07-368 RESOLUTION NO. 07-368
WHEREAS, on November 21, 2006, the City Council of the City of Beaumont,
Texas, passed Resolution No. 06-354 awarding a contract in the amount of$748,540 to
McInnis Construction of Silsbee, Texas, for the construction of a community center at
Central Park located at the corner of Fannin and Fourth Streets; and,
WHEREAS, Change Order No. 1, executed on May 18, 2007, was required for
additional excavation work thereby increasing the contract amount by $9,101.40 which
increased the total contract amount to $757,641.40; and
WHEREAS, Change Order Nos. 2 and 3, executed on June 20, 2007, and August
16, 2007, were required for additional completion days due to weather conditions with no
change to the total contract amount ; and
WHEREAS, Change Order No. 4 is required for the installation of a fence on the
west side of Fourth Street thereby increasing the contract amount by $32,450 for a total
contract amount of$790,091.40.
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order No. 4
increasing the contract amount by $32,450 for a total contract amount of$790,091.40 for
the construction of a community center at Central Park located at the corner of Fannin and
Fourth Streets.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 6th day of
November, 2007. _..`` (i MQy`1
A.
/ W toot&,
CA' � - ayor Becky Ames -
��� =�