HomeMy WebLinkAboutRES 07-298 RESOLUTION NO. 07-298
WHEREAS, on June 14, 2006, the City Council of the City of Beaumont, Texas,
passed Resolution No. 06-185 awarding a contract in the amount of $2,778,000.00 to
Landmark Structures, Fort Worth, Texas, for the Proposed 2 MG Elevated Water Tank at
Dishman Road Project; and,
WHEREAS, Change Order No. 1,approved by City Council on September 26,2006,
increased the contract amount by $114,489.00 for a total contract amount of
$2,892,489.00; and
WHEREAS, Change Order No. 2, approved by City Council on December 19,2006,
increased the contract amount by $147,700.00 for a total contract amount of
$3,040,189.00; and
WHEREAS, Change Order No. 3, dated May 15, 2007, increased the contract
amount by $9,400 for a total contract amount of$3,049,589.00; and
WHEREAS, Change Order No. 4 is required to provide for "extra work" for the
installation of additional electrical equipment associated with the construction of the second
and third floors, making water and sanitary provisions for the construction of future
bathroom facilities on the second and third floors, and replacing the gate valve with a
butterfly valve,thereby increasing the contract amount by$22,400.00 which increases the
total contract amount to $3,071,989.00.
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order No. 4
increasing the contract amount by$22,400.00 for a total contract amount of$3,071,989.00
for the Proposed 2 MG Elevated Water Tank at the Dishman Road Project.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 2"d day of
October, 2007.