THAT the FY 2008 Capital Program is hereby adopted. The Capital Program is
substantially in the form attached hereto as Exhibit "A". A public hearing was held
September 4, 2007, in the City Council Chambers, City Hall, Beaumont, Texas.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 25th day of
September, 2007.
it,
i v - May r ecky Ames -
j
PUBLIC WORKS PROJECTS
FY 2008-2012
Recommended
Time Schedule
Design or Construction Phase Estimated Cost FY 2008-2009
Babe Zaharias Drive $ 1,420,000
Calder- Main to Phelan 49,500,000 [1]
Cartwright/Corley-Ditch 100d 1,200,000 [2]
Concord IV - E.Lucas to Hwy. 105 16,000,000 [3]
Dowlen - College to Walden 11,840,000 [4],[5]
Dowlen - US 69 N to Delaware 10,600,000 [4]
Downtown Improvements
Neches - College to Laurel 1,500,000
Willow and Park - College to North 2,470,000 [6]
Pearl Street - Calder to North 570,000
Future Improvements 2,400,000
Fannett Road 630,000 [4]
Fannin Street-4th to 11th 6,300,000
Gulf-Live Oak to Delaware 2,260,000
Hayes Gully 2,790,000 [7]
Illuminated Street Markers
Signalized Intersections-160 Locations 1,000,000
Laurel - IH-10 to Office Park 4,700,000 [4]
Magnolia-Delaware to E. Lucas 5,240,000
Main - Calder to Blanchette 6,800,000
North Street - ML King to Twenty-Third 7,560,000
Old Dowlen - Dowlen to Hwy. 105 6,100,000 [8]
Phelan - Major to Keith 4,800,000
Regina-Howell to Thomas 1,600,000
Rolfe Christopher - US 69 S to Virginia 5,500,000
School Sidewalk Program 1,000,000
Seventh Street - IH-10 to Laurel 4,200,000
Street Rehabilitation 3,000,000
Washington - IH-10 to ML King 16,650,000
Washington - Langham to Major 6,710,000 [4],[9]
Wendelin/Kelly 710,000
Total Design or Construction Phase $ 185,050,000
[1] Includes FEMA Funding of$23,665,180 and other potential funding of$1,950,000.
The estimated cost to the City is$23,884,820.
[2] This is a joint participation project with DDff6.The estimated cost to the City is$1,200,000.
[3] Includes Federal Highway Administration funding of 80 percent up to$7,375,000.
[4] Air Quality issues will not be determined until a later date and could effect project timeline.
[61 Includes Federal Highway Administration Funding of$2,764,80.
[6] Includes Federal Highway Administration Funding of$512,000 for the section of Willow between North and Crockett.
[7] This is a participation project with 131306.The estimated cost to the City is$700,200
[8] includes TxDOT funding up to$4,000,000.
[9] Includes Federal Highway Administration Funding of$3,080,000.
Exhibit"X
PUBLIC WORKS PROJECTS
FY 2008-2012
Recommended
Planned Prolects Estimated Cost FY 2008-2012
Avenue A-Washington to U.S.69 S $ 7,350,000
Galdwood Outfall 5,500,000
College Street - IH-10 to Goliad 7,690,000
Delaware - Concord to Dowlen 12,100,000
Dowlen - Delaware to Gladys 7,500,000
East Lucas-U.S.69 N to Pine Street 12,600,000
Eleventh Street - Washington to US 69 15,750,000
Gladys Street - IH-10 to Dowlen 8,400,000
High School Ditch 9,130,000
Madison - Irving to Grove 2,470,000
Magnolia - Laurel to Delaware 7,860,000
Moore Street Relief 5,880,000
North Main Street - Calder to RR Tracks 1,890,000
Phelan - IH-10 to Dowlen 16,380,000
Pine Street - IH-10 to Crockett 3,780,000
Sabine Pass-Emmett to M.L. King 2,810,000
School Sidewalk Program 2,100,000
South Park Relief 7,880,000
Street Rehabilitation 12,000,000
Total Planned Projects $ 149,070,000
Total Public Works Projects $ 334,120,000
Exhibit"A"
GENERAL IMPROVEMENT PROJECTS
FY 2008-2012
Recommended
Time Schedule
Desion or Construction Phase Estimated Cost FY 2008-2009
Alice Keith Park Improvements $ 1,000,000
Athletic Complex Improvements 1,000,000
Athletic Complex Tennis Center 2,800,000
City Hall Improvements 1,000,000
Communication Building 1,000,000
Detention Facility Hike&Bike Trail 850,000
Downtown Event Center&Lake Park 7,000,000
Downtown Waterway 5,000,000
Fire Station Driveway Replacements 200,000
Fleet Facility Improvements 2,000,000
Martin Luther King,Jr.Park 900,000
Municipal Airport Improvements 4,500,000 [1]
911 Operations Center 3,200,000 [2]
Police Department Property Building 1,200,000
Property Acquisition and Site Improvements 1,000,000
Riverfront Park Improvements 2,000,000
Transportation Operations Shop 1,880,000
Tyrrell Historical Library Addition 2,200,000
Total Design or Construction Phase $ 38,730,000
Planned Projects FY 2008-2012
EMS Medic Station 2 $ 450,000
Fire Station Relocation/Administration 4,590,000
Public Health Department Building 2,500,000
Senior Center 2,300,000
Tyrrell Park Improvements 600,000
Total Planned Projects $ 10,440,000
Total General Improvement Projects $ 49,170,000
[1] Improvements to be funded by the Federal Aviation Administration on a 80120 and 90/10 basis.
The total commitment of the City is$600,000
[2] Includes insurance and funding from other sources
Exhibit"A"
WATER AND SEWER PROJECTS
FY 2008-2012
Recommended
Time Schedule
Design or Construction Phase Estimated Cost FY 2008-2012
Master Plan for Water&Sewer System $ 400,000
Water Department Security System 250,000
Water Projects:
2 MG Elevated Storage Tank on Dishman 3,300,000
36"Transmission Line 7,800,000
Ammonia Addition to Loeb Well 250,000
Automatic Flushing Devices 100,000
Leak Detection Project 350,000
Loeb Tank Rehabilitation 230,000
Water Line Extension on IH-10(between Brooks&Walden) 680,000
Water Line and Fire Hydrant Installation/Replacement 3,000,000
Water Rights Study 200,000
Water Treatment Plant Generators 3,300,000
Water Treatment Plant-Phase 1 5,200,000
Water Treatment Plant Improvements-Design Phase II 1,300,000
West Tank Rehabilitation 150,000
Sewer Projects:
54"Central Trunk Rehabilitation 5,500,000
54"West Trunk Outfall-Phase I&II 3,800,000
60"Trunk Line Rehabilitation 3,390,000
Degritter-Wastewater Treatment Plant 2,700,000
Dredge Ponds 1 and 2 at Wastewater Treatment Plant 1,200,000
East Lucas Relief Project 1,400,000
Filter Rehabilitation-Wastewater Treatment Plant 1,750,000
Florida Avenue&Fannett Road Interceptors 2,500,000
Grit Pump Replacement-Wastewater Treatment Plant 200,000
Lift Station Repairs 900,000
Primer Lift Station 740,000
Sanitary Sewer Line Extension on IH-10(Brooks to Walden) 680,000
Sanitary Sewer Rehabilitation-Small Mains(Pipe Bursting) 6,000,000
Wastewater Treatment Plant Generators 2,900,000
Wastewater Treatment Plant Master Plan 600,000
Wetlands Design&Rehabilitation 5,900,000
Exhibit"A"
WATER AND SEWER PROJECTS
FY 2008-2012
Recommended
Time Schedule
Design or Construction Phase (continued) Estimated Cost FY 2008-2012
Water/Sewer for Street Projects:
Calder-Main to Phelan $ 2,080,000
Concord Road-Phase IV-East Lucas to Hwy. 105 1,140,000
Dowlen Road-College to Walden 1,560,000
Dowlen Road-US 69 N to Delaware 910,000
Downtown Improvements:
Neches-Laurel to College 210,000
Willow and Park-North to College 700,000
Pearl Street-Calder to North 140,000
Fannin-Fourth to IH-10 453,000
Laurel-IH-10 to Office Park 490,000
Magnolia-Delaware to East Lucas 890,000
Main Street-Calder to Blanchette 840,000
North Street-ML lGng to Twenty-Third 960,000
Old Dowlen-Dowlen to Hwy. 105 530,000
Pearl Street-College to Calder 410,000
Phelan Blvd.-Major to Keith 800,000
Rolfe Christopher-US 69 S to Virginia 330,000
Seventh Street-IH-10 to Laurel 510,000
Tyrrell Park Road Resurfacing 1,560,000
Washington-IH-10 to ML IQng 2,000,000
Washington-Langham to Major 1,730,000
Total Design or Construction Phase $ 84,913,000
Exhibit"A"
WATER AND SEWER PROJECTS
FY 2008-2012
Recommended
Time Schedule
Planned Projects Estimated Cost FY 2008-2012
Lift Station Repairs $ 600,000
Sanitary Sewer Rehabilitation-Small Mains(Pipe Bursting) 4,000,000
Wastewater Treatment Plant Ground Improvements 1,000,000
Water Bottling Plant 1,500,000
Water Line and Fire Hydrant Installation/Replacement 2,000,000
Water Treatment Plant Improvements-Construction Phase 11 12,000,000
Water/Sewer for Street Projects:
Avenue A-Washington To US 69 S 650,000
College Street-IH-10 to Goliad 840,000
Delaware-Concord to Dowlen 2,730,000
Dowlen Road-Delaware to Gladys 630,000
East Lucas-US 69 N to Pine 1,920,000
Eleventh Street-US 69 N to Washington 440,000
Gladys Street-IH-10 to Dowlen 1,280,000
Gulf Street-Live Oak to Delaware 424,000
Madison-Irving to Grove 110,000
Magnolia-Laurel to Delaware 1,550,000
North Main Street-Calder to Railroad Tracks 170,000
Phelan Blvd-IH-10 to Dowlen 590,000
Pine Street-IH-10 to Crockett 440,000
Sabine Pass-ML King to Emmett 850,000
Total Planned Projects $ 33,724,000
Total Water and Sewer Projects $ 118,637,000