WHEREAS, on June 6, 2006, the City Council of the City of Beaumont, Texas,
passed Resolution No. 06-168 awarding a contract in the amount of$1,874,740.10 to L.
D. Construction for a contract for the Tyrrell Park and Downs Road Reconstruction Project;
and,
WHEREAS, Change Order No. 1 in the amount of($62,599.94)thereby decreasing
the amount to $1,812,140.16 is required for the decrease in construction item quantities:
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager is authorized to execute Change Order No. 1 in the amount of
($62,599.94) thereby decreasing the contract amount to $1,812,140.16.
BE IT FURTHER RESOLVED, that the City Manager is authorized to make final payment
in the amount of$97,260.81.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 18th day of
September, 2007.