HomeMy WebLinkAboutRES 07-229 RESOLUTION NO. 07-229
WHEREAS, bids were received for a contract for the construction of the
Consolidated Dispatch and Emergency Operations Center; and,
WHEREAS, N&T Construction Company, Beaumont,Texas, submitted a bid in the
amount of$2,434,000; and,
WHEREAS, Change Order No. 1 resulted in a deduction of$7,680 due to a discount
offered by the elevator contract, thereby decreasing the contract amount to $2,426,320;
and,
WHEREAS, Change Order No. 2 in the amount of$24,321 is required to remove
the partial existing suspended ceiling, replace a deteriorated partition, add furdown for
required duct space, add gyp board to some areas, change window framing at the
reception counter from pressed steel to aluminum, replace existing gyp board ceiling at
the Lobby to permit passage of ductwork, and add wooden furdowns at some windows.
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 2 in the amount of $24,321. The $24,321 will be subtracted from the Contingency
Allowance in the construction contract in the amount of$71,000 thereby leaving a balance
of$46,679. The contract amount will remain $2,426,320.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 14th day of
August, 2007. �r�` M�st