WHEREAS, on February 7, 2006, the City Council of the City of Beaumont, Texas,
passed Resolution 06-048, awarding a contract to Placo, LTD. in the amount of
$540,904.14 for the Sanitary Sewer Improvements Rehabilitation of the Florida Street Lift
Station Project; and,
WHEREAS, Change Order No. 1 in the amount of $76,340.19 was required to
adjust the scope of the work performed by the contractor thereby decreasing the contract
amount to $464,563.95; and,
WHEREAS, Change Order No. 2 in the amount of$19,192.68 thereby increasing
the contract amount to $483,756.63 is required to provide for 1) Removal of existing force
main as required for the installation of the proposed 27" sanitary sewer; 2) Additional 10
L.F. of 16" force main and an `oversized sleeve" to connect to the existing non-standard
cast iron force main; 3) Installation of a one inch (1") water service line, including RPZ
backflow preventor; 4) Rerouting of proposed 10" sanitary sewer due to underground
obstructions encountered including furnishing and installing two (2) additional sanitary
sewer manholes, additional 8 L.F. of 10"gravity sewer, additional structural backfill for the
10"gravity sanitary sewer, by-pass pumping of the existing 10"and new 27"sanitary sewer
lines, manhole demolition and flowable fill for the abandonment of the existing 10"sanitary
sewer line, and remobilization/demobilization; and 5) Delete the allowance for electrical
service installation. The Change Order will also adjust the contract time due to inclement
weather and additional work days. The additional days increases the total contract time
to 230 calendar days.
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order No. 2
in the amount of$19,192.68 thereby increasing the contract amount to $483,756.63.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 14th day of