HomeMy WebLinkAboutRES 07-192 RESOLUTION NO. 07-192
WHEREAS, bids were received forthe Hayes Gully Drainage Improvement Project;
and,
WHEREAS, Excavators and Constructors, LTD,submitted the low bid in the amount
of$3,668,172; and,
WHEREAS, such bid amount exceeded the amount of funds budgeted for this
project; and,
WHEREAS, Change Order No. 1 is required to remove a portion of the work in the
amount of$1,207,331.90,thereby decreasing the amount to$2,460,840.10,which is within
the amount budgeted for this project; and,
WHEREAS, City Council is of the opinion that the bid submitted by Excavators and
Constructors, LTD should be accepted along with the Change Order.
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
That the bid submitted by Excavators and Constructors, LTD for the Hayes Gully Drainage
Improvement Project in the amount of$3,668,172,with Change Order No. 1 in the amount
of $1,207,331.90 decreasing the contract amount to $2,460,840.10, be accepted by the
City of Beaumont.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 19th day of
June, 2007.
ose®s
r - M or ecky Ames -