HomeMy WebLinkAboutRES 07-071 RESOLUTION NO. 07-071
WHEREAS, on August 15, 2006, the City Council of the City of Beaumont, Texas,
passed Resolution No. 06-229 awarding a contract in the amount of$1,845,000 to Bruce's
General Construction, Inc., Beaumont, Texas, to furnish all labor, materials, supplies and
equipment to renovate the interior of the Julie Rogers Theatre; and,
WHEREAS, Change Order No. 1 was executed on November 2, 2006 for plumbing
repairs in the amount of$5,331.75 thereby increasing the contract to $1,850,331.75; and,
WHEREAS,the City Council of the City of Beaumont,Texas, passed Resolution No.
06-366 on December 5, 2006 approving Change Order No.2 in the amount of$65,380.01
increasing the contract amount to$1,915,711.76 for the installation of a concrete ramp and
handrails in auditorium entrances, additional plaster repair in the auditorium ceiling and
installation of rubber flooring in concession areas and elevator; and,
WHEREAS, Change Order No. 3 in the amount of $9,979.20 executed on
December 12,2006 for additional paint prep work on auditorium ceiling beams due to water
damage; and,
WHEREAS, Change orders Nos. 4, 5 and 6 were required as shown below:
Change Order No. 4 submitted December 12, 2006 in an amount of$17,139.07
includes:
1) Installation of new ceiling grids and ceiling tiles in foyers and stairways, control
room, 2"d floor concession area, and 1"floor meeting room. These areas were
omitted in the original plans and specifications. After construction began and
these areas were opened, damaged ceiling tiles and rusted grids were
discovered.
2) Installation of drywall in restrooms to accommodate raised floor. Drywall had to
be raised to accommodate raised floor in restrooms.
3) Add an overlay of sheetrock to paneled rooms previously scheduled for
repainting in the 2nd floor offices. The existing paneled walls were scheduled to
be painted but upon closer inspection, damage to the 30 year old paneling was
noted, thus the decision was made to overlay the paneling with sheetrock.
4) Furnish and install acoustical ceilings in 2"d floor north and south corridors. The
original plans called for recessed lighting with plaster ceilings. Since these are
office and dressing room corridors that will not be open to the public, it was
decided to lower the ceiling and install acoustical tiles.
5) Replacement of rusted metal studs found in restroom walls, janitor closets and
other interior room walls. The studs were rusted from water leaks not known until
existing walls were removed.
Change Order No. 5 submitted December 13, 2006 in an amount of$38,396.45
includes:
1) Leveling of restroom floors. After demolition of existing restrooms, it was
discovered that the floors were not level due to the settling of the foundation on
the north and south sides of the building. The floors need to be raised 2 Y2 to 3
Y2 inches to accommodate the installation of new restroom facilities and flooring.
After consulting with a structural engineer, it was determined that the floors could
be leveled by using concrete and a leveling compound. In addition, all plumbing
stub outs and drains must be raised to accommodate the new floor.
2) Additional stencil work by Conrad Schmitt in the west auditorium entrances.
Conrad Schmitt's original bid included lobby and hallway stencils. It was decided
to continue the same pattern in auditorium vestibules. The cost forthis additional
artistic stenciling is $2,278.50.
3) Plumbing repairs. These include replacing air conditioning drains, storm drains
and miscellaneous plumbing repairs.
Change Order No. 6 submitted December 21, 2006 in an amount of$71,896.82
includes:
• New and revised lighting. The original specifications for lighting were based on
a decorating scheme designed by LaBiche Architectural Group. The award of the
construction bid included an alternate bid item using the artistic design work by
Conrad Schmitt Studios for painting the lobby walls, auditorium and corridors.
The design scheme includes beautiful floral patterns in soft pastels,stenciled and
hand painted on wall panels and hand-painted ceiling murals.The lighting fixtures
originally specified are not appropriate for the new design concept. Included in
this change order are new chandeliers for the north and south lobbies. The
contractor allowed $10,715 in his bid for cleaning and repairing the existing
chandeliers. New chandeliers were selected after it was discovered that the
existing chandeliers had damage beyond repair. The price for the four
chandeliers including four mechanical lowering devices, new wiring and wall
controls, and installation is$55,060. In addition, new chandeliers not scheduled
for replacement in the original bid were selected for the Green Room, the Ticket
Lobby and corridors. Most of the cost was offset by the deletion of numerous
fixtures originally specified that did not compliment the architectural integrity of
the building.
Change Order Nos. 4, 5 and 6 in the total amount of $127,432.29 increased the
contract amount to $2,053,123.25; and,
WHEREAS, Change Order Nos. 7, 8 and 9 were required as shown below:
New Contract
Executed Reason Amount Amount
No. 7 1/18/07 Cabling installation $5,363.35 $1,986,589.78
No. 8 1/23/07 Drywall, insulation, cleanup and
debris removal, misc. a/c changes $6,444,82 $2,064,931.42
No. 9 1/23/07 Sheetrock for 14 doorways, tape,
float and paint, new base trim $3,606.75 $2,068,538.17
and,
WHEREAS, Change Order Nos. 10 through 15 were required as shown below:
Change Order No. 10 in an amount of$24,733.91 includes:
• Material and laborto modify auditorium floorto accommodate new seating layout.
Electrical and communication lines to be relocated in this area. Paint both the
auditorium and balcony concrete floors.
Change Order No. 11 in an amount of$5,092.50 includes:
• New laminate countertops and new cabinet doors in second floor concession
area.
Change Order No. 12 in amount of$9,284.10 includes:
• Miscellaneous repairs in various rooms and corridors.
Change Order No. 13 in an amount of$11,369.17 includes:
1) New carpet to be installed in the performer's dressing rooms,which includes one
on the 1st level and three on the 2nd level;
2) A brick paved floor similar to the southeast entrance lobby floor;
3) Installation of an automatic door, new glass and glazing of the sidelites and
transom and electrical connections.
Change Order Nos. 14 and 15 in an amount of$6,273.75 include:
• Remodel the wall inset to mount ADA drinking fountains and additional painting.
Paint the Rose Room and Chorus Dressing Rooms; and,
WHEREAS, Change Order Nos. 16 through 18 were required as shown below:
Change Order No. 16 in an amount of($16,366.65) includes:
1) Renovations to the Southeast entrance including new aluminum ceiling grid and
tiles, painting of exterior porch soffits, walls and doors and new light fixtures.
2) Construction of an enclosed glass cabinet to conceal the counter in Room 116
and miscellaneous electrical changes for security system and light fixtures.
3) Construction of a closet to conceal the main terminal switch for phone and
computers in 2nd floor offices.
4) Furnish and install new paper towel dispensers in restrooms.
5) 2nd Floor concession area will be equipped with one beverage dispenser. This
requires the installation of an ice bin and modification to the sink and
countertop.
6) Ticket Office-The original counter in the Ticket office was scheduled to remain
as it was constructed in 1982. It was not ADA compliant nor is it a convenient
and efficient workspace for staff. New cabinets will be designed to
accommodate computerized ticket processing equipment and additional staff
during crowded sales events.
7) Restroom Partitions - In the original design, the restroom partitions were to be
constructed of"Silestone", a natural quartz product. This material, usually used
for countertops, is heavy and not practical for restroom partition walls and
doors. This material was deleted and substituted with a lighterweight laminate
product resulting in a substantial credit of$42,352.00 to the cost of the project.
Change Order No. 17 in an amount of$15,064.00 includes:
1) Addition of two new circuits in the north and south corridors for lighting. Two
fixtures will be on separate circuits so as to not overload the main generator
backup circuit used in case of an emergency. This change was made at the
recommendation of the electrical engineer for this project.
2) Auditorium return air system was installed incorrectly during the 1982
renovation. Part of the system was not connected to the air conditioning unit
and electrical conduit was installed incorrectly. According to our Building
Services Manager, there had been unresolved problems with the air
conditioning unit but until the ceiling was opened during the remediation, the
cause of the problem was not known. This cost includes building a new 20 ft.
extension and removing existing grid and plaster.
3) Lamps in the auditorium ceiling are difficult to change because of limited
access. All light bulbs were replaced while scaffolding was in place.
Change Order No. 18 in the amount of$1,487.06 includes:
• Electrical upgrades to allow for control of the 2nd floor corridor lighting from the
control room. Allows staff to remotely flash lights to signify end of intermission;
and,
WHEREAS, Change Order No. 19 in the amount of $7,688.10 was executed on
February 21, 2007 for thirteen (13) new slab doors & four (4) new double units including
jambs, & installation of new doors and frames; and,
WHEREAS, Change Order No. 20 was required to install new front entry doors in
the amount of$29,925 thereby increasing the contract to $2,163,089.11.; and,
WHEREAS, Change Order No.21 was required to furnish and install new hardware
on secondary front entry doors and auditorium entrance doors on the first and second floors
in the amount of$38,778.60 thereby increasing the contract to $2,201,867.71; and,
WHEREAS, Change Order No.22 is required to refurbish the auditorium floor in the
amount of$28,184.89 thereby increasing the contract amount to $2,230,052.60.
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
That the City Manager be and he is hereby authorized to execute Change Order
No.22 in the amount of$28,184.89 thereby increasing the contract to $2,230,052.60.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 20th day of
March, 2007.
of 00 - Mayor Guy N. Goodson -
ua
W
�®�mw
� s
CHANGE ORDER
PROJECT: Improvements to the Julie Roger's CHANGE ORDER NO: 22
Theatre
CONTRACTOR: Bruce's General Construction, Inc. DATE: March 7, 2007
175 Reynolds Road ARCHITECT'S PROJECT NO.: 05004
Beaumont, TX 77707 CONTRACT DATE: August 9, 2006
CONTRACT FOR: Improvements
The Contract is changed as follows:
1. Saw cut concrete to allow for new electrical locations(using hydraulic wall saw). ADD $11,200.00
2. Water control,cleanup and protection for saw cut. ADD $1,500.00
3. Relocate electrical. ADD $7,104.48
4. Make ready and hook up balcony seat lighting ADD $2,095.50
5. Pour back concrete. ADD $3,200.00
6. Install 12 new light fixtures in rooms 116 and 107 as per attached quote and ADD $1,388.75
model Vs.
7. Install new Q fixture in rear stairway in place of ST fixture. ADD $229.02
8. Drywall repair after fixture is installed. ADD $125.00
9. Contractors Overhead and Profit @ 5% ADD $1,342.14
TOTAL $28,184.89
**See attached breakdowns
Not valid until signed by the Owner,Architect,and Contractor.
Theoriginal Contract Sum was................................................................................................................. $1,845,000.00
Net change by previously authorized Change Orders..................................................................................$356,867.71
The Contract Sum prior to this Change Order was....................................................................................$2,201,867.71
The Contract sum will be increased by this Change Order in the amount of ................................................$28,184.89
The new Contract Sum including this Change Order will be .....................................................................$2,230,052.60
The Contract Time will be increased by zero(00)days.
The date of Substantial Completion as of the date of this Change Order therefore is April 23,2007.
NOTE: The summary does not reflect changes in the Contract Sum or Contract Time, which have been authorized by
Construction Change Directive.
The LaBiche Architectural Group Bruce's General Construction, Inc. City of Beaumont
7999 Gladys ve ue, Suite 101 175 Reynolds Road P. O. Box 3827
Beaum:�01 x 777 06 Beaumont, Texas 77707 Beaumont, Texas 77704
By: By: By: /. 1
Date: _ 3.8'07 Date: Date: 3•Z " d 1
.4
M4,q 'yam
M
* 16306
OF
Request for Change To The
Contract Agreement
with
Bruce's General Construction, Inc.
Date: 03/02/07 Job No.: 688
RFC No.: 41
Mark all Invoices&
correspondence
with above Numbers
Job: City of Beaumont
Julie Roger Theater
Pearl St.
Description of Request
Saw cut concrete to allow for new electrical locations(using hydraulic wall saw $ 11 200.00
Water control cleanup and protection for saw cut $ 1,500.00
Relocate electrical $ 7,104.48
Make ready and hook up balcony seat li hting $ 2,095.50
Pour back concrete $ 3.200.00
Install 12 new ii ht fixtures in rooms 116 and 107 as per attached quote and model#'s' $ 1,388.75
Install new 0 fixture in rear stairway in place of ST fixture $ 229.02
Drywall repair after fixture is installed $ 125.00
Contractors Overhead and Profit 5% $1,342.14
Amount of this request: (add) $ 28 184.89
All terms and Conditions of the Original Contract remain unchanged except as hereby modified.
BRUCE'S GENERAL CONSTRUCTION,INC.
By:
Please indicate your acceptance by signing and returning immediately.
Accepted: ( ] Yes ( ] No DATE:
BY:
Ricky Lightfoot
5115 Belmont St.
Beaumont, TX 77707
Bruce's General Construction,Inc.
1175 Reynolds Rd.
Beaumont, TX. 77706
Attn Sean Tilley
Project: Julie Rogers Theatre
Provide all necessary material, labor and equipment to pour back holes made for
electrical relocation
Material: $ 600.00
Labor: $2100.00
Equip: $ 500.00
Total: $3200.00
Thanks,
Ricky Lightfoot
1
Beaumont Electric Inc,
826 Chamberlin Dr.
Beaumont Texas, 77707
409-842-3131
Fax 409-842-4506
Date:2127/07
RE.,Julie Rogers Theater
Attn:Bruces General Construction
1)Replacement of the type "ST"bagetelle fixture in stairway with one new type "Q"fixture
Labor $170.00
Material $ 38.20
10% $ 20.82
Total $229.02
2)Furnish and installation of(12)twelve new 2x4 lay-in 4 lamp metalux#2gr8432-unveb8l u,six
to be installed in room 107 and six to be installed in room 116.
Labor $ 586.50
Material $ 676.00
10% $ 126.25
Total $1,388.75
3)Relocate(23)twenty three floor boxes in the theater for seat isle lighting and connect the owner
furnished seat lights after installation.
Labor $4,165.00
Material $2,293.62
10% $ 645.86
Total $7,104.48
This price to include reworking of the existing underslab 314"pvc conduit to the new 4"floor box
locations that were marked by the seating contractor,repulling of the conductors with new,
installation of 318"greenfleld f/exable steel conduit with conductors from the new floor boxes to
the new seating lights and straped to the frame of the new seating mounting bar. This price does
not include busting,haling off, or patching the existing concrete.
4)Make ready and hook up(38)thirty eight 2nd floor balcony area seat isle lights.
Labor $1j615.00
Material $ 290.00
10% $ 190.50
Total $2,095.50
Feb 26 07 06: 57p p. 1
DAY _TIME
HOLES GOLDEN TRIANGLE, LLC ,�, �! ❑ CORE DRILLING
(409) 658-0103' FAX:(281)470=7848 ❑ JOB L'I4UOTE ( +; NXLL.SAWING
?-I ❑ WIRE SAW_
• (888)469-7070 r
�° _ ❑ SLAB SAWING
❑ CONCRETE BREAKING
r�-r'l ".•.•,' ""t•r ;.r.`L,,. Wle&D AND HAUL
PRICES QUOTED ARE VALID FOR.30 DAYS p..SPECIAL EQUIPMENT NEEDED
We can out it.-
CONTRACTOR'S NAME&ADDRESS r JOB LOCATION: �..-.
MAP PAGE
CONTACT:__Si P.O..#_
PHONE NO.:.—'- FAX JOB# P.O.#
DATE: SALESMAN FOREMAN JOB PHONE
PAGER MOBILE PHONE
JOB CONDITIONS NUMSER. -HOLE LOCATION DEPTH PRICE
YES No OF HOLES SIZE (Wall or Floor) OF HOLES PER HOLE NET PRICE
❑ ❑ ALL WORK MUST BE CLEAN AND LAID OUT."
❑ ❑ CUSTOMER&RESPONSIBLE FOR SCAFFOLD' k
❑ ❑ WATER AVAILABLE FEET
❑ ❑ ELECTRICITY AVAILABLE L FEET•
❑ ❑ WATER CONTROL NEEDED
❑ ❑ CONTRACTOR WILL PROVIDE ONE MAN
❑ ❑ IS WORK INSIDE FEET
❑ M ALL QUOTES BASED ON#4 REBAR ON'12",'
CENTERS UNLESS OTHERWISE NOTED.
❑ ❑ STAND-BY TIME$125.00 PER HOUR
CHEMICAL PLANT CONDITIONS AMOUNT OF DEPTH OF PRICE NET PRICE
FOOTAGE SAW CUT _ PER FOOT
❑ ❑ IS HOT PERMIT NEEDED /'�/�4 ►.�. 1;.}( y 1
❑ ❑ IS GASOLINE EQUIPMENT OK
❑ ❑ IS ELECTRICAL EQUIPMENT OK t'•%��• �' IM
rte•
❑ ❑ NOTIFICATION OF HAZARDS -• `
CUSTOMER RESPONSIBILITIES
1. ALL LAYOUT.DESIGN OR STRUCTURAL ISSUES ARE
THh HESPONS,IBILITIES OF THE HIRING CONTRACTOR. -
2. CUSTOMER IS RESPONSIBLE FOR TRAFFIC CONTROL
AND FOR SECURING ANY NECESSARY PERMITS. ADDITIONAL,REMARKS: PAYMENT DUE IN ADVANCE ON ALL COD'S
3. CUSTOMER IS RESPONSIBLE FOR COVERING
SLABS, fir .-.: � .e''": t r
OPENINGS IN uLABS,DEBRIS,SCAFFOLDING- `
WATER"CONTROC,
Ali
A. HOLES INCORPORATED CANNOT Be RESPONSIBLE
FOR SITE HAZARDS OR PROBLEMS THAT WE HAVE!, f'1 ', '� l'._, `-�f. - C:•� vJ ld'" Ci /y 'T�'/�' y
NOT BEEN ADVISED OF IN WRITING PRIOR'TO '
COMMENCEMENT OF WORK. = Gf uu�'✓�rJ� F ►'L{` � �,�r �J ,
5. PRICES BASED ON ONE MOVE IN UNLESS OTHERWISE, "b\ � � {L 4-L,. 4- �a�f i t =F.,.Lyv'•T
NOTED.
ACKNOWLEWED BY:
6. PRICES BASED ON 6"-8"CONCRETE UNLESS
OTHERWISE NOTED. l
NAME OF CO.
7. EXCLUDES: IDENTIFICATION OR LOCATION OF
UNDERGROUND UTILITIES;DISCONNECT OR CAPPING
OF UTILITIES;PROTECTION OF FINISH SURFACES; NAME i TITLE
FLOOR PREPARATION,GRINDING,OR MASTIC
REMOVAL.EXCAVATION,GRADING OR COMPACTION;
REMOVAL OF HAZARDOUS WASTE;SHORING OR
BRACING;FENCING;BARRICADES,PROTECTIVE
COVERS OR CANOPIES. WE CAN CUT IT !
DATE
The provisions of Executive Order 11246,38 U.S.C. 4212 and Section 503 are herein incorporated by reference.