HomeMy WebLinkAboutRES 07-022 RESOLUTION NO. 07-022
WHEREAS, on July 12, 2005, the City Council of the City of Beaumont, Texas,
passed Resolution No. 05-154 awarding a contract in the amount of$498,433 to Allco, Ltd.
for the Water Reclamation Plant Rock Track Basin Project; and,
WHEREAS, Change Order No. 1, passed by Resolution No. 05-216 on October 18,
2005, in the amount of$84,111, was required to furnish labor, equipment, and materials
to replace the two existing 48-inch reinforced concrete sanitary sewer pipes between the
he:adworks building and the junction box at the entrance of the Wastewater Treatment
Plant on Lafin Road thereby increasing the contract amount to $582,544; and,
WHEREAS, Change Order No. 2, in the amount of 21,724.24, is required to provide
the labor and equipment to break, remove and dispose of a twenty foot long by eighteen
foot wide by two foot thick reinforced concrete slab to accommodate the installation of the
48" Hobas pipe, thereby increasing the contract amount to $604,268.24.
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order No. 2
increasing the contract amount by$21,724.24 for a total contract amount of$604,268.24
for the Water Reclamation Plant Rock Track Basin Project.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 23rd day of
January, 2007.
�\