HomeMy WebLinkAboutRES 06-312 RESOLUTION NO. 06-312
BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF BEAUMONT:
WHEREAS, on May 17, 2005, the City Council of the City of Beaumont, Texas,
passed Resolution No. 05-125 awarding a contract in the amount of $2,094,178.15 to
Placo, Ltd., for the Downtown Improvements Pearl Street (Calder Avenue to College
Street), Bowie Street(Pearl Street to Main Street), and Liberty Street(Pearl Street to Main
Street) Interlocking Concrete Brick Pavers Project; and,
WHEREAS, Change Order No. 1, not requiring Council approval and dated June
16,2005,decreased the contract amount by$100,000 for a total amount of$1,994,178.15;
and
WHEREAS, Change Order No. 2, in the amount of $272,423.55, is required to
change the Scope of Work to include Orleans Street from Broadway Avenue to Liberty
Avenue, Broadway Avenue from Orleans Street east 180 feet, Liberty Avenue from
Orleans Street east 180 feet, and to replace 21 flourescent illuminated street name signs
with edge lit LED illuminated street name signs, thereby increasing the contract amount to
$2,266,601.70.
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be, and he is hereby authorized, to execute Change Order No. 2
in the amount of$272,423.55 increasing the contract amount to $2,266,601.70.
PASSED BY THE CITY COUNCIL of the City of Be mont this the 17th day of
October, 2006. %
i ,,�0 _
C) ; Mayor Guy N. Goodson -
w
4
.r`� INTER-OFFICE MEMORANDUM
M EL City of Beaumont,Texas
Engineering Division
Date: October 25, 2006
To: City Clerk's Office
From: Engineering dle__
Subject: DOWNTOWN IMPROVEMENTS PEARL ST. (CALDER AVE. TO COLLEGE ST.)
BOWIE ST. (PEARL ST.TO MAIN ST.)AND LIBERTY ST. (PEARL ST.TO MAIN ST.)
INTERLOCKING CONCRETE BRICK PAVERS- CHANGE ORDER 2
COMMENTS
Attached for your records is a copy of the above agreement. City Council approval was given October 17, 2006
by Resolution 06-312. Thank you.
ml
Attachment
CITY BEAUMONT
DATE: September 28, 2006
PROJECT: DOWNTOWN IMPROVEMENTS PEARL STREET (CALDER
AVE. TO COLLEGE ST.) BOWIE STREET (PEARL STREET
TO MAIN STREET), AND LIBERTY STREET (PEARL
STREET TO MAIN STREET) INTERLOCKING CONCRETE
BRICK PAVERS
OWNER: CITY OF BEAUMONT
CONTRACTOR: Placo, LTD
CHANGE ORDE NO. 2
THE FOLLOWI G CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE
HEREBY MADE:
Change the Scope of Work to include: Orleans Street from Broadway Avenue to Liberty Avenue,
Broadway I Lvenue from Orleans Street east 180 feet and Liberty Avenue from Orleans Street east
180 feet. This will increase the contract amount by $200,000.00.
Replace twenty-one (21) flourescent illuminated street name signs with edge lit LED illuminated
street name signs. This will increase the contract amount by $72,423.55.
The total increase to the contract per this change order is $272,423.55.
ORIGINAL CONTRACT AMOUNT: $ 2,094,178.15
NET FROM PREVIOUS CHANGE ORDERS; $ 1,994,178.15
TOTAL AMOUNT OF THIS CHANGE ORDER: $ ^272,423.55
PERCENT OF THIS CHANGE ORDER: 13.01%
TOTAL PERCENT CHANGE TO DATE: 13.01%
NEW CONTRACT AMOUNT: $2,266,601.70
CONTRACT TIMES IS NOT AFFECTED BY THIS CHANGE ORDER
AC
CE D BY-
4.�__
CONTACTOR
APPROVED BY:
01IL � aff2:��
J IS P. COLBERT, P.E. CITY ENGINEER
can, A.
TOM A.WARNER, P.E.
DIRECTOR OF PUBLIC WORK
KYLE HAYES, CITY MANAGER '� QyMO/Vp��1�11
ATTESTED BY:
O W
CITY CLERK
01�f1 /0
-1 ..