HomeMy WebLinkAboutRES 06-267 RESOLUTION NO. 06-267
WHEREAS, on February 8, 2005, the City Council of the City of Beaumont, Texas,
passed Resolution No. 05-037 awarding a contract in the amount of$3,071,100 to Brystar
Contracting, Inc.,for the Water Reclamation Plant Aeration Lagoon Improvements Project;
and,
W HEREAS, Change Order No. 1 in the amount of$348,608 was required for"extra
work" performed by the Contractor to change the pipe material from the specified 72 inch
CMP to rubber gasketed 72 inch RCP, delete the aerators mooring system and slab,
heaters and heating cable, delete the electric conduits from the control panel to each
aerator, delete the electrical manhole and replace it with a junction box, and delete the
asphalt coating for the 72 inch CMP pipe thereby increasing the contract amount to
$3,419,708; and,
WHEREAS,Change Order No.2 in the amount of$127,215.76 is required to reduce
the amount of footage of 72" Reinforced Concrete pipe by 119.6 linear feet despite a
restocking fee of two 72" 45 degree bends. Additional changes include electrical work at
junction Box "A", adjustments to enlarge Junction BOX "B", adding a block wall and plug,
leaving the sheet piling in Lagoon #1, rental on additional sheet piling required in Lagoon
#2, plugging of the pipe between Lagoon #1 and Lagoon #2 and bypass pumping for
Junction Box "A" and Junction BOX "B;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order No. 2
in the amount of$127,215.76 thereby increasing the contract amount to $3,546,923.76.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 12th day of
September, 2006.