RESOLUTION NO. 05-189
WHEREAS, on December 16, 2003, the City Council of the City of Beaumont,
Texas, passed Resolution No. 03-271 awarding a contract in the amount of$11,029,000
to Craig Sheffield &Austin, Inc. for the Water Treatment Plant 14 Million Gallons Per Day
(MGD) Expansion and Miscellaneous Improvements Project; and,
WHEREAS, Change Order No. 1, passed by Resolution No. 04-143 on June 29,
2004, in the amount of$1,377,912.01 was required for extra work to install two additional
filter units with all the related appurtenances for a complete operation system, modify the
fill beneath the chemical storage, clean debris in the chemical storage area and change
the existing piping in the chemical building thereby increasing the contract amount to
$12,406,912.01; and,
WHEREAS, Change Order No. 2, passed by Resolution No. 05-003 on January 4,
2005, in the amount of$28,475.60 was required for extra work to add a caustic injection
line at the chemical feed vault, change service pumps to sump pumps, add concrete
sidewalks around the east stairway at Administration Building entry, add pipe support
braces for 60-inch influent settled water piping in filter gallery, and add embedded
waterstop at the filter side of the cold joint required to install the geotextile drainage layer
thereby increasing the contract amount to $12,435,387.61; and,
WHEREAS, Change Order No. 3 passed by Resolution 05-130 on May 24, 2005,
was required to slope pulsator slabs to the drains, install a concrete plug for the 36-inch
drain pipe located at the south clearwell, stabilize fill material and 27-inch pipe under 72-
inch pipe, investigate leak south of the clearwell and fill sink hole in access road, provide
additional hatches and lifting hooks along the filter gallery roof, provide and install
compressed air piping and related appurtenances from the existing chemical building to
the chemical storage area, apply a NSF rated coating on all wet surfaces at the pulsators
and rapid mix basin, provide and install five 30-inch insert magnetic flow meters at the
pulsators instead of five 30-inch flanged magnetic flow meters, add galvanized steel
access ladder at fluoride storage area, provide and install Altivia chlorine dioxide
generators and control revisions, provide additional circuit breakers, conduits, and wire for
pipe heat trace, install Marsh-McBirney insert magnetic flow meter instead of polysonicflow
meter at CF-V2, extend pulsator basin sample piping to the existing filter gallery, reroute
existing 4-inch sanitary sewer force main to the existing manhole on Pine Street, repair
items on the final punch list of the 5 MG Clearwell Project increasing the contract amount
by $249,396.54 thereby increasing the contract amount to $12,684,784.15; and,
WHEREAS, Change Order No. 4 is required to dig and locate the leak on the
existing 48 inch water transmission line, install a light pole, install two 48 inch butterfly
vavles at the high service pump station discharge connection, install water hose stations,
pressure and caustic taps at the new filters in the amount of$90,450.34 thereby increasing
the contract amount to $12,775,234.49;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order No. 4
increasing the contract amount by$90,450.34 for a total amount of$12,775,234.49 forthe
r
• `extra work' described above for the Water Treatment Plant 14 Million Gallons Per Day
(MGD) Expansion and Miscellaneous Improvements Project.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 30th day of
August, 2005.