HomeMy WebLinkAboutRES 05-130 RESOLUTION NO. 05-130
WHEREAS, on December 16, 2003, the City Council of the City of Beaumont,
Texas, passed Resolution No. 03-271 awarding a contract in the amount of$11,029,000
to Craig Sheffield &Austin, Inc. for the Water Treatment Plant 14 Million Gallons Per Day
(MGD) Expansion and Miscellaneous Improvements Project; and,
WHEREAS, Change Order No. 1, passed by Resolution No. 04-143 on June 29,
2004, in the amount of$1,377,912.01 was required for extra work to install two additional
filter units with all the related appurtenances for a complete operation system, modify the
fill beneath the chemical storage, clean debris in the chemical storage area and change
the existing piping in the chemical building thereby increasing the contract amount to
$12,406,912.01; and,
WHEREAS, Change Order No. 2, passed by Resolution No. 05-003 on January 4,
2005, in the amount of$28,475.60 was required for extra work to add a caustic injection
line at the chemical feed vault, change service pumps to sump pumps, add concrete
sidewalks around the east stairway at Administration Building entry, add pipe support
braces for 60-inch influent settled water piping in filter gallery, and add embedded
waterstop at the filter side of the cold joint required to install the geotextile drainage layer
thereby increasing the contract amount to $12,435,387.61; and,
WHEREAS, Change Order No. 3 increasing the contract amount by $249,396.54
for a total amount of$12,684,784.15 is needed to slope pulsator slabs to the drains, install
a concrete plug for the 36-inch drain pipe located at the south clearwell, stabilize fill
material and 27-inch pipe under 72-inch pipe, investigate leak south of the clearwell and
fill sink hole in access road, provide additional hatches and lifting hooks along the filter
gallery roof, provide and install compressed air piping and related appurtenances from the
existing chemical building to the chemical storage area, apply a NSF rated coating on all
wet surfaces at the pulsators and rapid mix basin, provide and install five 30-inch insert
magnetic flow meters at the pulsators instead of five 30-inch flanged magnetic flow meters,
add galvanized steel access ladder at fluoride storage area, provide and install Altivia
chlorine dioxide generators and control revisions, provide additional circuit breakers,
conduits, and wire for pipe heat trace, install Marsh-McBirney insert magnetic flow meter
instead of polysonic flow meter at CF-V2, extend pulsator basin sample piping to the
existing filter gallery, reroute existing 4-inch sanitary sewer force main to the existing
manhole on Pine Street, repair items on the final punch list of the 5 MG Clearwell Project;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order No. 3
increasing the contract amount by $249,396.54 for a total amount of$12,684,784.15 for
the `extra work'described above for the Water Treatment Plant 14 Million Gallons Per Day
(MGD) Expansion and Miscellaneous Improvements Project.