REGULAR MEETING OF THE CITY COUNCIL
COUNCIL CHAMBERS APRIL 20, 2004 1:30 P.M.
AGENDA
CALL TO ORDER
* Invocation Pledge Roll Call
Presentations and Recognition
Public Comment: Persons may speak on scheduled agenda items 1-2/Consent
Agenda
Consent Agenda
GENERAL BUSINESS
1. Consider approving a one (1) year contract for the purchase of fittings, pipes and
couplings for use in the Water Utilities Division
2. Consider authorizing the City Manager to increase the Barscreen Area and Belt
Press Conveyor Improvements Project amount for"extra work"
COMMENTS
Councilmembers/City Manager comment on various matters
* Public Comment (Persons are limited to 3 minutes)
EXECUTIVE SESSION
* Consider matters related to contemplated or pending litigation in
accordance with Section 551.071 of the Government Code:
Claim of Stephen Thompson
Persons with disabilities who plan to attend this meeting and who may need auxiliary aids
or services are requested to contact Pat Buehrle at 880-3725 a day prior to the meeting.
i
1
April 20, 2004
Consider approving a one (1) year contract for the purchase of fittings, pipes and couplings for
use in the Water Utilities Division
i
CIE1. ...Jl!.
City of Beaumont
Council Agenda It
� = • � g em
TO: City Council
FROM: Kyle Hayes, City Manager
PREPARED BY: Kirby Richard, Central Services Director
MEETING DATE: April 20, 2004
AGENDA MEMO DATE: April 13, 2004
REQUESTED ACTION: Council approval of a one (1) year contract for the purchase of
fittings, pipes and couplings.
RECOMMENDATION
Administration recommends award of an annual contract for purchasing fittings, pipes and
couplings to various vendors at the unit costs reflected in the attached bid tabulation, with an
estimated total annual expenditure of$397,130.14.
BACKGROUND
Bids were requested for an annual contract for couplings, brass fittings, plastic tubing and other
water-related materials for use by the Water Utilities Division.
The materials are used in the repair of existing water lines, installation of new water service lines,
and in the maintenance of existing water mains and meters. The materials are utilized to maintain
adequate water service throughout the City.
Forty-seven(47)vendors were notified, with four (4) responding with bids. Specifications stated
that the contract would be awarded to the low bidder per section. The low bidder per section is
shaded for identification in the attached bid tabulation. The estimated annual expenditure to each
vendor under the contract is as follows: $65,961.19 to Coburn Supply of Beaumont, $307,590.65
to Golden Triangle Pipe of Beaumont, $17,466.30 to Hughes Supply of Lufkin, and $6,112.00
to Rural Pipe of Jasper.
BUDGETARY IMPACT
Funds are available for this expenditure in the Water Utilities Division's operating budget.
i
Annual Contract for Fittings, Pipe and Couplings
April 13, 2004
Page 2
PREVIOUS ACTION
None.
SUBSEQUENT ACTION
None.
RECOMMENDED BY
City Manager, Central Services Director, and Public Works Director.
BID TABULATION FOR FITTINGS,PIPES,AND COUPLINGS
BID NUMBER:RF0104-18
BID OPENING DATE:MARCH 25,2004,2 PM
��- COBURN SUPPLY GOLDEN TRIANGLE PIPE HUGHES SUPPLY 'I RURAL PIPE
IBEAUMONT,TX BEAUMONT TX LUFKIN TX JASPER TX
Item# Qty Description Unit Total Unit Total Unit Total Unit Total
BENDS
1 30 6" bend M.J.45 degree D.I.w/accessory pack E$6 00 $1,680.00 $52.70 $1;581.00 $49.26 $1,477.80 $46.23 $1,386.90
2 15 6" bend M.J.90 degree D.I.w/accessory pack 00 $915.00 $57.35 $860,25 $53.81 $80715 $53.81 $807.15
i
3 10 8"bend M.J.45 degree D.I.w/accessory ack $79.00 $790.00 $73.95, $739.50 $69.73 $697.30 $65.001 $650.00
4 10 8"bend M.J.90 degree D.I.w/accessory pack $87.00 $870.00 $81.60 $816.00: $76.93 $769.30 $76.00 $760.00
5 j 40 6"x 6"tee M.J.x M.J.x swivel D.I.w/accessory pack $110.00 $4,400.00 $102.10' $4,084.00' $96,251 $3,850.00 $96.25 $3,850.00
6 6 -16"-2"tapped cap M.J.x 2"F.I.P.T.D.I.w/accessory pack $36.00 $216.00 534.10'' $204.60 $32.211 $193.26 $32.21 $193.26
MANUFACTURER BID: T ler Tyle, I T ler/Star Pipe** Sigma**
Total-Bends $8,871.00� n $7647.31 1
BOLTED COUPLINGS
7 300 3/4"bolted coupling S.B.411-010501-003 steel pipe size 1 $16.60 $4,980.00 $10.75 $3,225.00 $17.061 $5,118.00 $9.25 $2,775.00
8 100 V bolted coupling S.B.411-013201-003 steel pie $20.90 $2,090.001 $11.10! $1,110100 $21.48 $2,148.00 $10.46 $1,046.0011
9 30 1-1/4"bolted coupling S.B.411-016601-003 steel pipe size $22.22 $666.60 $11.60 $348.00' $22.84 $685.20 $12.31 $369.30
10 60 1-1/2"bolted coupling S.B.411-019001-003 steel pipe size $22.22 $1,333.20 $13.85 $831.00 $22.84 $1,370.40 $13.20 $792.00
11 200 2"bolted coupling S.B.411-023801-003 steel pipe size $29.51 $5,902.00 $15.70 $3,140.00 $30.31 $6,062.00 $18.77 $3,754.00
12 r:20 2"bolted coupling S.B.441-000263-900 C.I.pipe size $17.80 $5,340.00 $15.3$ $4,605.00 $18.29 $5,487.00 $15.50 $4,650.00�
E14 2-1/2"bolted coupling S.B.441-000288-900 C.I.pipe size $19.05 $381.00 $19.85: $397,00 $19.57 $391.40 $20.00 $400.00
6"bolted coupling S.B.441-000722-900 C.I.pipe size $35.80 $7,160 00 $40.50 $8,100.00 $36.78 $7,356.00 $40.00 $8,000.0015 8"Bolted coupling S.B.441-000945-900
C.I.pipe size $51.46 $2,573.00 $51.20 $2,560.00 $52.86 $2,643.00' $50.00 $2,500.00
16 50 1 12"Bolted coupling S.B.441-000945-900 C.I.pipe size $74.28 $3,714 00 $85.60' $4,280.04' $76.30 $3,815.00 $85.38 $4,269.00
MANUFACTURER BID: Ford Smith Blair 1 Ford Dresser
Total-Bolted Couplings $34,139.80 $28,596.00* $35,076.00 $28 555 30
FULL CIRCLE CLAMPS
17 25 2-1/2"X 7-1/2"full circle clamp S.B.226-00027507- $23.69 $592.25' $23.90 $597.50 $24.341 $608.50 $23.57 $589.25
000 for cast iron
18 10 4"x 7-112"full circle clamp S.B.226-00048007-000 $31.69 $316.90 $29.75 $297.50 $32.56 $325.60 $24.21 $242.101'
19 10 3-4"x 7-1/2"full circle clamp S.B.226-00037507-000 $30.19 $301.90' $26.80 $268.00 $31.02 $310.20 $24.76 $247.60
20 IO 3-4 x 7-1/2" full circle clamp S.B.226-00040007-000 $27.94 $279.40 $27.80 $278.00 $28.71 $287.10 $27.25 $272.50
�21 25 6"x 7-1/2"full circle clamp S.B.226-071007 for A.C.pipe $32.20 $805.00 $35.65 $891.25 $33.08 $827.00 $28.57,
2E2 300 2"x 7-1/2"full circle clamp S.B.226-023807 for C.I.pipe $23.38 $7,014.00.. $22.05 $6,615.00 $24.02 $7,206.00 $23.57 $7,071.00,
23 65 6"x 7-1/2"full circle clamp S.B.226-069007 for C.I.pipe $3720 $2,093.001- $35.15 $2,284.75 $33.08 $2,150.20 $33.49 $2,176.85
24 50 6"x 12-1/2"full circle clamp S.B.226-069012 for C.I.pipe $43.40 $2,170.00 $56.20 $2,810.00 $44.59 $2,229.50 $44.11 $2,205.50
25 15 6"x 15"full circle clam S.B. 226-069015 for C.I.pie $50.96 $764.40 $65.30 $979.50 $52.36 $785.40 $52.53 $787.95
26 30 6"x 20"full circle clamp S.B.226-069020 for C.I.pipe $69.87 $2,096.10 $94.65 $2,839.50 $71.78 $2,153.40 $74.28 $2,228.40
27 25 8"x 7-1/2"full circle clamp S.B.226-090507 for C.I.pie $32.81 $820.25. $42.05 $1,051.25 $33.71 $842.75 $32.39 $809.75
28 12 8"x 20"full circle clamp S.B.226-0900520 for C.I.pipe $77.81 $933.72 $111.10 $1,333.20 $79.93 $959.16 $85.60 $1,027.20,;
29 25 12"x 7-1/2"full circle clamp S.B.226-132007-000 for $36.69 $917.25 $57.70 $1,442.50 $45.57 $1,139.25 $48.01 $1=$000
Class 50 cast iron pipe
I
30 16 12"x 12-1/2"frill circle clamp S.B.226-132012 for C.I.pipe $70.94 $1,135.04 $92.85 $1,485.60 $72.88 $1,16608 1 $77.01 1 $1,232.16
MANUFACTURER BID: Fortl Smith Blair Ford Romac
Total-Full Circle Clams S20,239.21 $23,173.55 $20 990 14 $20,804.76
SERVICE SADDLES
31 5 2"x 3/4"service saddle for PVC pipe $7.67 $38.35 $7,30 $36.50 $7.89 $39.45 $8.57 $42.85
32 50 2"x 1"service saddle for SDR-26 PVC pipe $7.67 $383.50 $7.30 $365.00 $7.89 $394.50: $8.57 $428.50
33 5 6"x 3/4"service saddle for C-900 e i
P $17.80 $89.00 $16.90 $84.50: $18.29 $91.451 $19.86 $99.30
34 5 8"x 3/4"service saddle for C-900 pipe $24,91 $124.55 $23.65 $118.25 $25.60 $128.00 $27.81 $139.05
35 100 6"x 1"service saddle for C-900 PVC pipe $17.80 $1,780.00 $16.90. $1690.00 $18.29 $1,829.001 $19.86 $1,986.00
36 40 8"x 1"service saddle for C-900 PVC pipe $24.91 $996.40 $23.65 $946.00 $25.60 $1,024.00 $27.81 $1,112.40
37 5 2"x 3/4" service saddle for cast iron pipe $8.14 $40.70 $14.15 $70.75 $29.86 $149.30 NB $0.00
38 24 2"x l"service saddle for C.I.pi e N/B $0.00 $14.15 $339.60 $29.86 $716.64 NB $0.00
39 20 6"x 1"service saddle for single strap 910-967 $17.80' $356.00 $23.35 $467.00 $18.29 $365.80 $19.86 $397.20.
40 100 6"x 1"service saddle D.S.for cast iron 1 $40.09 $4,009.00 $40.95. $4,095.00 $41.18 $4,118.00 $44.74 $4,474.00
41 25 9"-1-1/2"service saddle D.S.for cast iron _ $45.841 $1 146.001 $46.85 $1,171.25 $47.091 $1,177.25 $51.15 $1,27975
i
F. COBURN SUPPLY GOLDEN TRIANGLE PIPE HUGHES SUPPLY RURAL PIPE
BEAUMONT,TX BEAUMONT TX LUFKIN TX JASPER,TX
Item# Qty Description Unit Total Unit Total Unit Total Unit Total
42 30 6"x 2"service saddle D.S.for cast iron $50.36 $1,510.80 $51.45 $1,543.50 $51.74 $1,552.20 $56.20 $1,686.00
43 60 8"x 1"service saddle D.S.for cast iron $49.62- $2,977.20 $50,70 $3,042.00 $50.96 $3,057.601 $3,322.20
MANUFACTURER BID: I Ford James Jones/Cambrid"e Ford A.Y.McDonald
Total Service Saddles $13,451.50 $13 969 35 $14,643.19 $14,966.25,
it COUPLINGS
44 50 3/4"female coupling bomze F.I.P.T. $5.15 $257.50 $4.75 $237.50 $5.30 $265.00 $5.05 $252.50
45 50 1"female coupling bronze F.I.P.T. $6.80 $340.00 I' $6.30 $315.00 $6.99 $349.50 $6.85 $342.50
46 20 1-1/2"female coupling bronze F.I.P.T. $17.18; $343.60 $16.75 $335.00 $17.66 $353.20 $18.24 $364.80',
47 20 2"female couplinE bronze F.I.P.T. $20.28 $405.60 $19.95 $399,00 $20.83 $416.60 $21.72 $434.40
48 1000 3/4"male coupling bronze M.I.P.T. $4.93 $4,930.00 $4.45 $4,450.00 $5.07' $5,070.00 $4.80 $4,800.00
49 400 1"male coupling bronze M.I.P.T. $5.76 $2,304.00 $5.25 $2,100.00'' $5.92 $2,368.00 $5.69 $2,276.00
50 100 1-1/2"male cog ling bronze M.I.P.T. $13.64 $1,364.00' $13.10 $1,310.00 $14.02 $1,402.00 $14.26 $1,426.00
51 200 2"male coupling bronze M.I.P.T. $19.44 $3,888.00 $19.05 $3,810.00' $19.98 $3,996.001 $20.77 $4,154.00
52 100 3/4"meter coupling bronze 90 degree w/M.I.P.T. $4.07, $407.00 $3.20 $320.00 $4.18 $418.00 $4.28 $428.00,
53 200 1"meter coupling bronze 90 degree w/M.I.P.T. $5.82 $1,164.00' $4.35 $87' $5.98 $1,196.00 $5.941 $1,188.00
54 25 3/4"coupling bronze straight meter coupling $2.77 $69.25! $1.90 $47.50.. $2.85 $71.25 $2.81'i $70.25
55 25 1"meter coupling bronze strai gh t w/M.I.P.T.
$4.27 $106.75 $2.97 $74.25 $4.39 $109.75: $4.49 $112.251
56 400 3/4"union coupling bronze $5.86 $2,344.00 $5.75 $2,300.00 $6.02 $2,408.00 E$6.70.85 �$2,340.00
57 200 1"union coupling bronze $6.65 $1,330.00 $6.15 $1,230.00 $6.84 $1,368.00 $1,340.00
58 50 1-1/2"union couping bronze $18.69 $934.50 $18.80' $940.00 $19.21 $960.50 $20.49 $1,024.50..
59 80 2"union coupling bronze $25.56 $2,044.80 $25.40 $2,032.00 $26.26: $2,100.80 $27.66 $2,212.80
60 400 3/4"bronze coupling $3.35' $1,340.00: $2.67 $1,068.00' $2.741!, $1,096.00 $1.071 $428.00
61 300 1"coupling bronze ------------
$5.71 $1,713.00 $4.03 $1,209.00' $4.67 1 401.00,
$ , $1.63 $489.00
62 100 1-1/2"coupling bronze $12.41 $1,241.00' $8.75 $875.00 $10.151 $1,015.00 $3.45 $345.00
63 100 2"coupling bronze American made $20.53 $2,053.00 $14.45 $1,445.00 $16.78 $1,678.00 N/B $0.00
MANUFACTURER BID: Ford/Merit/Cooper James Jones/Merit/Combrid Ford/Merit A.Y.McDonald**
i
Total-Couplings $28,580.00 $25,367.25 $28042.60 $24 028.00
BUSHINGS
64 200 1"X 3/4" bushing bronze 1"M.I.P.T.x 3/4"F.I.P.T. $3.35 $670.00 $2.36 5472.00 $2.74 $548.00 $1.07 $214.00
65 60 1-1/2"x t"bushing bronze 1-1/2"M.I.P.T.x F.I.P.T. $8.14 $488.40 $5.72' $343.20 $6.64 $398.40 $2.33 $139.80
66 60 2"X 3/4"bushin bronze M.I.P.T.x F.I.P.T. $10.04 $602.40 $7.05' $423.00 $8.20 $492.00 $4.16 $249.60
67 60 2"x 1"bushing bronze 2"M.I.P.T.x I"F.I.P.T. $10.04 $602.40 $7.05 $423.00' $8.20 $492.00 $4.16 $249.60
68 40 2"x 1-1/2"bushing bronze 2"M.I.P.T.x 1-1/2" $10.04. $401.60 $7.05 $282.00' $8.20' $328.00 $3.46: $138.40
F.I.P.T
FACTURER BID: Merit/Cooper .Merit Merit Matco**
Total-Bushin s $2 764.80 $1 943.20' $2,258.40 $991.40
ANGLESTOPS
69 600 3/4"angle ball stop bronze $19.68 $11,808.00 $12.60' $7,560.00 $20.22; $12,132.00 $21.72:1 $13,032.00
70 300 1"angle ball lock wing stop bronze $29.66 $8,898.00 $31.20 $4 360.00 $30.47 $9,141.00 $32.72 $9,816.00;I
71 25 1-1/2"angle lock wing ball stop M.LP.T.x Fl . $58.86 $1,471.50 $56.50 $1,412'650 $60.47 $1,511.75 $64.94 $1,623.50
72 40 2"angle lock wing ball stop M.LP.T.x Flg. $69.45 $2,778 00 $66.75 $2,670.00' $2,854.00 $76.63 $3,065.20
73 10 3/4"corp.ball stop bronze $14.45, $144.50 $14.00 $140.00 $14.85 $148.50 $15.22,' $152.20
74 400 1"core.ball stop bronze $18.84 $7,536.00 $18.40 $7,360.00 $19.36 $7,744.00 $20.02 $8,008.0011
75 20 1-1/2"corp.ball stop bronze $38.14 $762.80 $38.40 $768.00 $39.18 $783.60 $41.01' $820.20 11
76 50 1-1/2"curb ball stop t-head $42.69 $2,134.50 $41.60. $2,080.00 $43.86 $2,193.00 $47.11 $2,355.50
77 60 2"corp.ball stop bronze $62.44 $3,746.40 $63.50 $3,810,00 $64.15 $3,849.00i $67.84 $4,070.40
78 300 314"curb ball stop bronzet-head $14.67: $4,401.00 $10.95 $3,285.00 $15.08 $4,524.00 $16.191 $4,857.00,1
79 200 1"curb ball stop bronze t-head $22.80 $4,560.00 $23.10 $4,620.00 $23.42. $4,684.00 $25.16 $5,032.001
80 too 2"curb ball stop bronze t-head $62.44 $6,244.00 $63.25 $6,325.00 $64.151 $6,415.001 $68.89 $6,889.00
81 60 1-1/2 meterflan a bronze w/F.I.P.T $44.88 $2,692.80 $11.65 $649.00 $25.00 $1,500.00. $12.47 $748.20
82 100 2"meter flange bronze with F.I.P.T. $71.57 $7,157.00 $15.25' $1,525.00 $27.00 $2,700.00 $16.27 $1,627.00
83 300 3/4"--I -nze 90 de ee $3.82 $1,146.00 $2,68. $804.00 $3.12 $936.00 $1.25 $375.00
84 300 1"ells bronze 90 degree $6.20 $1,860.00 $4.36 $1,308.00 $5.08 $1,524.00 $1.92 $576.00
85 60 1-1/2"ells bronze 90 degree $12.43 $745.80 $8.74 $524,40 $10.15' $609.00 $3.83 $229.80
86 100 2"ells bronze 90 degree $20.05 $2,005.00 $14.10 $1,410.00 $16.38 $1,638.00 $6.23 $623.00:1
87 300 3/4"street ells 90 degree bronze $5.25 $1,575.00 $3.70 $1,110.00 $4.29 $1,287.00 $1.63 $489.0011
88 200 I"street ells 90 degree bronze $8.60 L:�$1,720.001 $6.05. $1,210.00 $7.03 $1,406.00' $2.70 $540.00
89 60 1-1/2"street ells 90 degree bronze $17.18 1 030.801 $12.10 $726.00- $14.04 $842.40 $5.37 $322.20
i
1 COBURN SUPPLY GOLDEN TRIANGLE PIPE HUGHES SUPPLY 1 RURAL PIPE
1 BEAUMONT,TX BFAUMONT TX LUFIN,TX JASPER TX
1,Item#' Qty Description Uni Total Unit Total Unit Total Unit Total
90 200 2"street ells 90 degree bronze $29.14 $5,828.00 1
$20.50 $4,100.00' $23.801 $4,760.00 $9.11 $1,822.00
MANUFACTURER BID: Merit Ford Coo er Merit/James JoneslCambrid'Ford Merit A.Y.McDonald
Total-Anele Stops $80 245.10 $62,806.90 $73,182.25 $67,073 20 7.
NIPPLES
91 800 3/4"x2"bronze nip le $1.30 $1,040.00 $0.90 $720.00' $1.12 $896.00 $0.85 $680.00111
92 600 3/4"x 6"bronze nipple $3.32 $1,992.00 $2.30 $1,380,00..1 $2.84 $1,704.00, $2.17 $1,302.00
93 400 1"x 3"bronze nie $2.51 $1,004.00 $1.75 $?00.00'> $2.16 $864.001 $1.871 $748.00
94 100 1"x 6"bronze nipple $4.85 $485.00 $3.37 $337.00 $4.15 $415.00 $3.60 $360.00'
95 50 1-1/2"x 4"bronze nipple $5.77 $288.50 $4.01' $200.50: $4.94' $247.00 $4.29' $214.50
96 100 2"x 4"bronze nipple $7.41 $741.00 $5.15 $515.00' $6.36 $636.00 $5.51 $551.00
97 100 2"x 6"bronze nipple $10.97 $1,097.00 $7.60 $760.00 $9.38 $938.001 $8.14 $814.00
MANUFACTURER BID: Merit Merit r Merit Mateo
Total-Nipples $6 647.50 $4,612.50' $5 700 00
$4669.50 1
TUBINGS
98 5,000 3/4"X 500' PVC C.T.S.tubing $0.17 $850.00 $0.12 $600.00 $0.15 $750.001 $0.12 $600.00
99 20,400 V x 300'PVC C.T.S.tubing $0.18 $3,672.00; $0.19 $3,876.00, $0.25 $5,100.00 $0.18 $3;672.00
100 2,000 1-1/2"x 100'PVC C.T.S.tubing $0.36 $720.00 $0.38 $760.00 $0.47 $940.00 $0.361 $720.00
101 2,000 2"x 100'PVC C.T.S.tubing 1 $0.461 $920.00 $0.60 $1,200.00 $0.74 $1,480.00 $0.56 $1,120.00
MANUFACTURER BID: Charter Plastics NuMex NuMex NuMex
Total-Tubin s _-j $6,162.00 $6,436.00 $8 270.00' $6112.00
FIRE HYDRANT BURY
102 100 Fire Hydrant American Flo Control 13-84-B 3'6"bury $852.00, $85,200.00 $875.00 $87,500.00 $873.88 $87,388.00'N/13 I $0.00
MANUFACTURER BID: M&H/Kenned *** American Flo Control American Flo Control -�I
Total-Fire Hydrant B $85 200 00 S87,500.00- $87,388.00 $0200 00 00
VALVES AND VALVE TAPS
103 60 6"gate valve M.J.x M.J. $270.00 $16,200.00 $259.10 $15,546.00 $256.20 $15,372.00 $232.00 $13,920.00
104 30 8"gate valve M.J.x M.J. $429.00 $12,870.00 $404,40 $12,132.00 $408.00 $12,240.00 $369.00 $11,070.00
105 30 Darling 865 tapping valve(Kennedy,Mueller)American $380.00 $11,400.00 $345.10 $10,353.00 $357.40 $10,722.00 $232.00 $6,960.00
made
i
106 20 8"tapping valve tap x M.J. $553.00 $11,060.00 $524.20 $10,484.00' $548.91 $10,978.20 $498.00 $9,960.00
107 12 12"gate valve M.J.,ductile iron,NRS,resilient seat,wrench $870.00 $10,440.00 $780,50' $9,366.00 $848.66 $10,183.92 $767.00 $9,204.00
accessory pack,American flow Control 2512,American mad'�e
108 1 4 12"tapping gate valve M.J.,ductile iron,NRS,resilient seat, $1,270.00 $5,080.00 $1,168.40 $4,673'.b0 $1,256.02 li $5,024.08 $1,139.95 $4,559.80
wrench nut,ace.pack,Amer.flow cont.2512,American made
MANUFACTURER BID' Kenned American Fl,Control`American Flo Control American Flo Control�American Flo Control I AVK***
Total-Valves&Valve Ta�s $67 050 00 $62 554.60 $64,520 20 $55,673.80
METER BOXES
109 300 #37T cast iron(solid)lid for#37 marked water, $16.31 $4,893.00 $14.95 $4,485.00 $16.31 $4,893.001 NB $0.00
concrete meter box American made
110 80 #65 cast iron meter box lid 2 piece,marked water. $28.39 $2,271.20 $26.05 $2,084.00 $28.11 $2,248.80 NB $0.00
111 200 Cast iron meter box,Ford YMBHC 141233 straight $91.20 $18,240.00 $113.951 $22,790.00 $93.75 $18,750.00 N/B $0.001
locking ball inlet with compression nut 10"high
dual check lid,for 5/8"-3/4"meters
it
2 50 Cast iron meter box Ford YL111-444 straight ball $137.21 $6,860.50 $171.30 $8,565.00 $140.95 $7,047.50 NB,
inlet with compression nut 10"high,1"female I.P.T.
outlet non-locking lid,for 1"meter
113 25 Cast iron grade adjuster Ford LYGA 1-1/4"-3" $99.96 $2,499.00` $40.40 $1,010.00 $69.43 $1,735.75 N/B
$0.00
complete for Ford cast iron box YL 141233
114 24 2"Cast iron Ford 12-23/32"high protector meter box $244.77 $5,$74.4$: $305.601 $7,334.40 $251.43 $6,034.32 NB $0.0011
complete with 3 piece lid marked Water.FPMB-7
Standard finish.
115 24 2"Ball inlet Ford BFP 83-777W M.I.P.T.x Fig for a $84,82 $2,035.68 $108.00
$2,592.001 $87.13 2
$ ,091.12 NBi $0.00,1
Ford cast iron meter box
116 24 2"Ball inlet Ford BFP 31-777 M.I.P.T.x Fig for a $57.64 $1,383.36' $73.40 $1,761.60 $59.21 $1,421.04 NB $0.001
Ford cast iron meter box
117 12 2" Ford protector cast iron meter box lid end pc $10.20 $122.40 $12.75 $153.00 $10.49 $125.88 NB
$0.001
FPMBL-E7
118 12 2"Ford protector cast iron meter box lid center c. _ $24.68 $296.16 $30.85 $370.20 $25.36 $304.32 NB
_ $0.00
i
COBURN SUPPLY GOLDEN TRIANGLE PIPE HUGHES SUPPLY RURAL PIPE
BEAUMONT,TX BEAUMONT TX LUFKIN TX I IASPFR'TX
Item# Qty Description Unit Total Unit Total Unit Total Unit Total
FPMBL-C7
119 12 1-1/2"Ford ball valve BFP83-676W F.I.P.T.x Flg for $56.31 $675.72 $71.70 $860.40: $57.84 $694.08 NB $0.00
installing 1-I/2"meter.
120 12 1-1/2"check valve bronze Ford HFS31-666.F.I.P.T.x $47.54 $570.48' $55.85 $670.20 $48.84, $586.08 NB $0.001
fl .
MANUFACTURER BID: Ford Ford Fmd/Southera
Total-Meter Boxes $45.721.981 $0.00 $0.00
VALVE BOXES
121 40 Valve box top C.I.5-1/4"x 10"American made $14.00 $560.00 $12.65 $506.00 $15.51 $620.40 NB $0.00
122 60 Valve box lid C.I.for 5-1/4"box American made $9.00 $540.00 $8.50 $510.00' $9.63 $577.80 N/B $0.00
123 100 Valve box riser 5-1/4"x 2-1/4"C.I.American made $17.00 $1,700.00 $10.00 $1,000.00' $9.90 $990.00;N/B $0.00
124 100 Valve box bottom 5-1/4"Tylere 562-S $24.00 $2,400.00 $22.55 $2,255.00 $26.40 $2,640.00 N/B $0.00
125 100 Valve box top 5-1/4"x 16"long shaft cast iron for Tyler $20.00 $2,000.00 $18.50 $1,850.00' $21.73 $2,173.00 NB $0.00
562-S American made
MANUFACTURER BID i Tyler T Ier EJIW
Total-Valve Boxes $7,200.00 $6,121.00 $7,001.20 _ $0.0011
FIRE HYDRANT EXTENSIONS �-
126 8 12"fire hydrant extensions for B84 American Flo Control NIB
$174.25 $ $1,400.00i $155.00 $1,240.00
fire hydrant,no substitutes
127 4 18"fire hydrant extensions for B84 American Flo Control N/B $198.95 $795.80 $197.00 $788.00 $177.00 $708.00
fire hydrant,no substitutes
128 2 24"fire hydrant extensions for B84 American Flo Control N/B $224.35 $448.70 $222.00 $444.00 $199.00 $398.00,11
fire hydrant,no substitutes
MANUFACTURER BID: American..Flo Control American Flo Control H Brant Re air Parts***
Total-Fire Hydrant Extensions $000 $2 638.50- $2 632 00 $2 346 00
CHECK VALVES
129 1 25 3/4"brass swing check valve with teflon seat,F.I.P.T. $25.30 $632.50 $21.40 $535.00 $27.00 $675.00 NB $0.00
130 50 1"brass check valve with teflon seat,F.I.P.T $30.80 $1,540.00 $29.50'' $1,475.00 $36.00 $1,800.00 NB $0.00
131 10 1-1/2"brass check valve with teflon seat,F.LP.T. $57.36 $573.60 $48.25 $482.50' $63.00 $630.00 N/B
132 10 2"brass check valve with teflon seat,F.I.P.T. $84.98 $849.80 $70.35 $703.50 $91.29 $912.90 NB $0.00'1
MANUFACTURER BID: Hammond/NIBW Hammond Hammond
Total-Check Valves -$359590T $3,196.00 $4,017.90, $0.00
MECHANICAL JOINT RESTRAINER
133 150 6"mega lug mechanical joint restrainer series $25.39 $3,808.50 $24.80 $3,720.00 $26.74 $4,011.00 $21.47 $3,220.50
2000PV for PVC C900 class 150 pipe bolts i
and gaskets packaged w/mega lug
134 140 8"mega lug mechanical joint restrainer series $34.77 $4,867.80 $34.10 $4,774.00 $36.77 $5,147.80 $29.911 $4,187.40
2000PV for PVC C900 class 150 pipe bolts
and gaskets package w/mega lug
135 40 12"mega lug mechanical joint restrainer series $64.48 $2,579.20 $63.00 $2,520.00 $68.00 $2,720.00' $58.541 $2,341.601
2000PV for PVC C900 class 150 pipe;bolts
r,
and gaskets packaged w/mega lug
136 200 3/4"x l"cou ling union bronze NB $6.25 $1,250.00 ;$6.93 $1,386.00 NB $0.00
137 50 6"x 12"Sleeve Ductile Iron,M.J.,Amer.made $39.00, $1,950.00 $54.50 $2,725.00 $36.03 $1,801.50'NB $0.00
138 50 8"x 12"Sleeve Ductile Iron,M.J.,Amer.made $52.00 $2,600.00 $69.25 $3,462.50 $48.00 $2,400.00''N/B �_ $0,00'!
MANUFACTURER BID: Ford T lei Ebba EbbalT lei Not Stated
Total-Mechanical Joint Restrainer $15 805.50 $18 451.50 $17 466.30 $9 749.50
BID AMOUNT
$425,674.29 $408,327.501 $424,914.88 $242617.02
Recommended'Award $65,961.19 S307,590.651 $17 466.30 1 112.00
*Denotes bid award to local vendor based on sales tax impact analysis. $6
**Denotes bid not awarded due to vendor bidding import items within the section,which is prohibited by the specifications requiring American made products only.
***Substitutes for specified product manufacturer not allowed.
i
2
April 20,2004
Consider authorizing the City Manager to increase the Barscreen Area and Belt Press Conveyor
Improvements Project amount for"extra work"
i
City of Beaumont
Council Agenda Item
TO: City Council
FROM: Kyle Hayes, City Manager
PREPARED BY: Joseph G. Majdalani, Water Utilities Manager
MEETING DATE: April 20, 2004
AGENDA MEMO DATE: April 12, 2004
REQUESTED ACTION: Council approval of a resolution authorizing the City Manager to increase
the Barscreen Area and Belt Press Conveyor Improvements Project
amount for "extra work."
RECOMMENDATION
Administration recommends approval of increasing the Barscreen Area and Belt Press Conveyor
Improvements Project amount by$163,626 to restore the structural integrity of 1500 square feet of walls
and ceiling surface area inside the wet well of the main pump station at the Wastewater Treatment Plant
by installing 4-inch thick repair mortar and reinforcement, to install 80 mils of protective coating to the
restored surface area, and to provide diversion pumping during construction.
BACKGROUND
The interior walls and ceiling of the existing suction well at the Wastewater Treatment Plant built in the
early 1950s have deteriorated and require major rehabilitation. The primary goals of the project are to
restore the structural integrity of the wet well, stop the deterioration of its walls and ceiling, and prolong
its life, in order to provide customers with uninterrupted and adequate service.
BUDGETARY IMPACT
Funds for the project are available in the Capital Improvement Funds.
PREVIOUS ACTION
Resolution 03-172 in the amount of 833,786 was passed by City Council on August 19, 2003.
SUBSEQUENT ACTION
None.
RECOMMENDED BY
City Manager, Public Works Director, and Water Utilities Manager.
W UAllcoChanOrdBarScreen.wpd
April 12, 2004
i
APPROVAL Ole CONTRACT CHANGE
Change Order No. 1
Date:April 12,2004
Project: City of Beaumont
Barscreen Area and Belt Press Conveyor Improvements
Owner: City of Beaumont
11.0.Box 3827
Beaumont,Texas 77704
Contractor: Allco, Inc.
P.O.Box 3684
Beaumont,Texas 77704
To tite Owner: Approval of the following contract change is requested.
Reason for Change:To increase the contract amount for"extra work"performed by the Contractor to restore the
structural integrity of 1500 square feet of walls and ceiling surface area inside the wet well of the main pump station
at the Wastewater Treatment Plant,to install 80 mils of protective coatingto therestored surface area,and to provide
diversion pumping during construction.
ORIGINAL CONTRACT AMOUNT $833,786.
THIS CHANGE ORDER:
Description Net Change
Restore 4-inch of the walls and ceiling interior surface area of the
suction well at the Wastewater Treatment Plant with repair mortar. + 97,800.
Install 80 mils of protective coating over the restored surface area. + 28.500.
Provide diversion pumping during construction. + 37,326.
TOTAL AMOUNT OF THIS CHANGE ORDER: $163,626.
TOTAL REVISED CONTRACT AMOUNT INCLUDING
THIS CHANGE ORDER: $997,412.
CONDITION OF ChIANGE:
"Contractor acknowledges and agrees that the adjustments in contract price and contract time stipulated inthis Change
Order represents fitll compensation for all increases and decreases in the cost of,and the time required to perform the
entire work under Contract arising directly or indirectly from this Change Order and all previous Change Orders.
Acceptance of this waver constitutes an agreement between Owner and Contractor that the Change Order represents
an all inclusive,mutually agreed upon adjustment to the Contract,and that Contractor will waive all rights to file a
claiut on this Change Order after it is properly executed."
Recommended By: Approved,By: Accepted By:
Jo el;h(;. Rlajdalani, P.G. City of Beaumont Allco Inc.
Water Utilities Manager Owner Contractor
Date: _ Date: 13 O
i
C �y o l-I eaurno n
REGULAR MEETING OF THE CITY COUNCIL
COUNCIL CHAMBERS BERS AIPRIL 20, 2004 1030 P.M.
CONSENT AGENDA
Approval of minutes
Confirmation of committee appointments
A) Approve a contract for the purchase of automotive batteries for use by the Fleet Management
Division
B) Approve a resolution accepting maintenance of the water and sanitary sewer improvements in
Calder Addition subdivision
i
A
......
City of Beaumont
Council Agenda Item
TO: City Council
FROM: Kyle Hayes, City Manager
PREPARED BY: Kirby Richard, Central Services Director
MEETING DATE: April 20, 2004
AGENDA MEMO DATE: April 7, 2004
REQUESTED ACTION: Council approval of a contract for the purchase of automotive
batteries.
RECOMMENDATION
Administration recommends award of a one (1) year contract for purchasing automotive batteries
to Battery Warehouse of Orange at the unit costs stated below with an estimated total annual
expenditure of$20,783.10.
BACKGROUND
Bids were requested for a one (1)year contract for purchasing automotive batteries for use by the
Fleet Management Division to maintain city-owned vehicles and equipment. The specifications
require fixed pricing for the most commonly used battery types, and a percentage discount off list
price for other batteries as needed during the contract period.
Nine (9)vendors were notified with three(3) responding with bids as reflected in the attached bid
tabulation. The product line quoted by Battery Warehouse has been reviewed by Fleet
Management and meets specifications set forth in the bid.
The sales tax impact analysis formula has been applied to the local vendors' bids, but did not alter
the bid standings.
BUDGETARY IMPACT
Funds are available for this expenditure in the Fleet Management Division's operating budget.
PREVIOUS ACTION
None.
i
One(1)Year Contract for Automotive Batteries
April 7, 2004
Page 2
SUBSEQUENT ACTION
None.
RECOMM ENDED BY
City Manager and Central Services Director.
i
ANNUAL CONTRACT FOR AUTOMOTIVE BATTERIES
BID OPENING DATE: THURSDAY,APRIL 1,2004
BID NUMBER: RF0304-25
Name of Vendor Battery Warehouse-Orange Interstate Batteries NAPA Auto Parts
Address 1111 16th Street 6008 College St. 3266 College St.
City/State Orange,Texas Beaumont,Texas Beaumont,Texas
Contact Name Whit Baker Joseph Kingsbury Jerry Roberts
Phone Number (800)409-3545 (409)860-4200 (409)833-8900
Brand Bid G.E.S.Alliance Johnson Controls/Enertec NAPA
Discount Offered Off List Price 35% 40% 30%
App. Qty. Battery Type/BCI# Unit Cost Extended Cost Unit Cost Extended Cost Unit Cost Extended Cost
180 78U-7(34/78) $38.95 $7,011.00' $41.97 $7,554.60 $39.96 $7,192.80
132 31S $38.95 $5,141.40 $38.47 $5,078.04 $49.24 $6,499.68
~ 115 65 $38.95 $4,479.25 $36.85 $4,237.75 $40.99 $4,713.85
18 4D $69.95 $1,259.10 $66.47 $1,196.46 $87.49 $1,574.82
12 58 $31.95 $383.40 $39.95 $479.40 $38.72 $464.64
14 75 $31.95 $447.30 $31.26 $437.64 $34.22 $479.08
14 8D $79.95 $1,119.30' $75.$1,057.98 $97.43 $1,364.02
16 U1(SP40) $24.95 $399.20 $35.77 $572.32 $: 3.24 $371.84
17 58R $31.95 $543.15' $31.47 $534.99 _ $38.721 $658.24
Total Bid Amount $2078 .10' $21,149.181 $23,318.97
i
B
City of Beaumont
Council Agenda Item
TO: City Council
FROM: Kyle Hayes, City Manager
PREPARED BY: Joris P. Colbert, City Engineer
MEETING DATE: April 20, 2004
AGENDA MEMO DATE: April 6, 2004
REQUESTED ACTION: Council consider a resolution accepting maintenance of the water and
sanitary sewer improvements in Calder Addition subdivision.
RECOMMENDATION
Administration recommends approval of the water and sanitary improvements for Lots 1 - 10, Block 43
in the Calder Addition subdivision.
BACKGROUND
The aforementioned improvements in the subdivision passed final inspection from the Water Utilities
Division on April 6, 2004.
BUDGETARY IMPACT
None.
PREVIOUS ACTION
None.
SUBSEQUENT ACTION
None.
RECOMMENDED BY
City Manager, Public Works Director and City Engineer.
EngAgenCalderAddsk.wpd
April 6,2004
i
\ 2.,
5„ Y
iG 3
i R
E '
i EE
-- LOCATION ` "
Por ROA W ---
_� Por
5�„
Ec 5 - • t}��'
o f Po k
�� K RU • • ,��:'
HUSK
0 T Pork_, - • '• Q
c 54 '
IAP FIR
.T
0 GRUCKE i
_VICINITY MAP E°
N.T.S.
r �
C
CALDER ADDITION
SUBDIVISION
i
APPROVAL OF CONTRACT CHANGE
Change Order No. 1
Date: April 12, 2004
Project: City of Beaumont
Barscreen Area and Belt Press Conveyor Improvements
Owner: City of Beaumont
P.O. Box 3827
Beaumont, Texas 77704
Contractor: Allco, Inc.
P.O. Box 3684
Beaumont, Texas 77704
To the Owner: Approval of the following contract change is requested.
Reason for Change: To increase the contract amount for "extra work"performed by the Contractor to restore the
structural integrity of 1500 square feet of walls and ceiling surface area inside the wet well of the main pump station
at the Wastewater Treatment Plant,to install 80 mils of protective coatingto the restored surface area,and to provide
diversion pumping during construction.
ORIGINAL CONTRACT AMOUNT $ 833.786.
THIS CHANGE ORDER:
Description Net Change
Restore 4-inch of the walls and ceiling interior surface area of the
suction well at the Wastewater Treatment Plant with repair mortar. +$ 97,800.
Install 80 mils of protective coating over the restored surface area. + 28.500.
Provide diversion pumping during construction. + 37,326.
TOTAL AMOUNT OF THIS CHANGE ORDER: $ 163,626.
TOTAL REVISED CONTRACT AMOUNT INCLUDING
THIS CHANGE ORDER: $ 997,412.
CONDITION OF CHANGE:
"Contractor acknowledges and agrees that the adjustments in contract price and contract time stipulated in this Change
Order represents full compensation for all increases and decreases in the cost of,and the time required to perform the
entire work under Contract arising directly or indirectly from this Change Order and all previous Change Orders.
Acceptance of this waver constitutes an agreement between Owner and Contractor that the Change Order represents
an all inclusive, mutually agreed upon adjustment to the Contract, and that Contractor will waive all rights to file a
claim on this Change Order after it is properly executed."
Recommended By: Approved By: Accepted By:
Jo e151� G. IVlajdalani, P.1;. City of Beauirront Allco, Inc.
Water Utilities Manager Owner Contractor
Date: �' ��( late: J Date: /3 D