HomeMy WebLinkAboutRES 94-238 RESOLUTION NO.
WHEREAS, on February 8, 1994, City Council awarded a Contract to Affolter
Contracting, Inc.for Remediation and Drainage Improvements for the Fire Training Center
in the amount of $980,681.70; and,
WHEREAS, Change Order No. 1 changed the scope of the project, but did not
increase the total cost nor the time of the Contract; and,
WHEREAS, Change Order No. 2 increased the contract amount by $20,892.90 for
replacing 310.6 tons of stabilized sand at $16.00 per ton for a credit of$4,969.60) with 206.9
cubic yards of concrete at $125.00 per cubic yard (at a cost of $25,862.50) increasing the
contract amount to $1,001,574.60; and,
WHEREAS, Change Order No. 3 is being requested to increase the contract amount
by $217,321.85 because numerous instances of unsuitable subgrade were encountered which
increased the amount of excavation, backfill and cement stabilized sand material;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order No. 3 as
stated above with Affolter Contracting, Inc.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the/° day of
1994.