WHEREAS, on July 24, 1990, City Council authorized the City Manager to
enter into a contract with Cutler Repaving, Inc., in the amount of $1,226,186.85 for the
recycling and repaving of 20 sections of asphalt streets in the first phase of the 1990 Street
Maintenance and Rehabilitation Program; and,
WHEREAS, during the course of the project, there were two change orders.
Change Order No. 1 was an increase in the amount of $239,026.00 for additional street
drainage and stability; Change Order No. 2 was a deduction in the amount of $86,758.05;
and,
WHEREAS, the project was inspected by the Engineering Division and found
to be completed in conformance with the contract requirements;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be, and he is hereby, authorized to accept the project as complete
and issue final payment in the amount of $92,464.84 to Cutler Repaving, Inc.