HomeMy WebLinkAboutRES 90-167 I R E S O L U T I O N WHEREAS on May 2, 1988, City Council awarded a contract to Daniels Building and Construction, Inc. for the remodeling and conversion of the Szafir Building to house the new Texas Energy Museum; and, WHEREAS, during the contract there were four change orders. Change Order 1 was a deduction in the contract of $22, 927. 00. Change Orders 2, 3 and 4 were additions in the contract in the amount of $5, 568. 00, $21, 375. 00 and $1, 102. 00. This resulted in a net change order of $5, 118. 00, bringing the total project price to $1,239,708. 00. On May 12, 1989, the building was accepted as substantially complete; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the City Manager be, and he is hereby, authorized to accept the project and make final payment to Daniels Building and Construction, Inc. in the amount of $61,930. 30. PASSED BY THE CITY COUNCIL of the City of Beaumont this the day of , 1990. - Mayor -