WHEREAS, on May 17 , 1983 the City of Beaumont entered
into an agreement with Fittz and Shipman for engineering services
in connection with the Highland Avenue TIP Project; and,
WHEREAS, due to a more detailed drainage study, it has
been discovered that more work is needed in an area between Iowa
Street and Florida Avenue than was previously determined;
NOW , THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT :
THAT the City Manager be, and he is hereby , authorized to amend the
agreement with Fittz and Shipman for engineering services in
connection with the Highland Avenue TIP Project by increasing the
design phase from $68,650 to $71 , 250 and the construction phase
from $73,600 to $75,200.
BE IT FURTHER RESOLVED that an extension of ten ( 10)
working days be added to perform the work.