HomeMy WebLinkAboutRES 84-116 R E S O L U T I O N
WHEREAS, the City of Beaumont entered into a contract with
John Bankston Construction & Equipment Rentals , Inc. in the amount of
$455,500 for Sanitary Sewer Contract 8B/9B; and,
WHEREAS, Change Order No. 2 has been recommended to adjust
the contract to reflect actual quantities of materials installed and
the contract completion date;
NOW , THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be, and he is hereby , authorized to execute
Change Order No. 2 to the contract with John Bankston Construction &
Equipment Rentals, Inc. , Sanitary Sewer Contract 8B/9B , thereby
decreasing the amount of the contract from $455,500 to 453,903 and to
pay John Bankston Construction & Equipment Rentals , Inc. $22,770. 15
in final payment.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the
day of
Mayor -