HomeMy WebLinkAboutRES 84-032 R E S O L U T I O N
WHEREAS, on January 1 , 1983 the City of Beaumont awarded a
contract to D & H Construction Company in the amount of $30,826 for
the construction of a covered play area at Magnolia Park; and,
WHEREAS, the project was completed forty-six (46) calendar
days after the contract completion date of August 3 , 1983 ; and,
WHEREAS, final payment is being requested in the amount of
$ 3,276.48 less liquidated damages of $1 ,150 ;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the construction of a covered play area at Magnolia Park is
hereby accepted by the City of Beaumont and that the City Manager be,
and he is hereby , authorized to make final payment to D & H
Construction Company in the amount of $2 ,126 .48.
PASSED BY THE CITY COUNCIL of the City of Beaumont this
the day of Llhrc.ac�� 19 .
Mayor -