WHEREAS, on July 13, 1982, the City of Beaumont awarded
a contract to Troy Dodson Construction Company in the amount of
$538 ,976.40 for the 1982 Street Rehabilitation Program - Project I ;
and,
WHEREAS, the project has been completed at a cost of
$532,505. 13 which is below contract price;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the 1982 Street Rehabilitation Program - Project I , is hereby
accepted by the City of Beaumont and the City Manager be, and he is
hereby , authorized to make final payment to Troy Dodson Construction
Company in the amount of $26,673.27.