HomeMy WebLinkAboutRES 82-370 R E S 0 L U T 1 0 N
WHEREAS, the City of Beaumont entered into a contract
with Greer Construction Company for Beaumont Water Canal Clearing
Contract No. 2 ; and.,
WHEREAS, Change Order No. 1 to said contract has been
proposed increasing the total cost by the sum of $6,576. 00 to provide
for the additional hours required to work under and adjacent to low
level Power lines near the Wiess Bluff pump Station; to remove
unknown quantities Of silt located below the water surface in Bunn' s
Bluff; and, to increase the square yards of earthwork to provide for
new and unforeseen repairs required at various locations on the 8. 1
miles of Wiess Bluff Canal; and,
WHEREAS, the project has been completed in accordance
with the plans and specifications;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be, and he is hereby, authorized to execute
Change Order No. 1 , in the amount of $6,576. 00, to the contract
between the City of Beaumont and Greer Construction Company for
Beaumont Water Canal Clearing - Contract No. 2 -1
BE IT FURTHER RESOLVED that the City Manager be, and he is
hereby, authorized to make final payment to Greer Construction
Company in the amount of $12,795- 70.
PASSED BY THE CITY COUNCIL of the City of Beaumont this
the _Nov day of 19A .
Mayor
&-