HomeMy WebLinkAboutRES 97-221 RESOLUTION NO. 7-ate
WHEREAS, on February 18, 1997, the City Council of the City of Beaumont,
Texas, awarded a contract to Excavators & Constructors, Inc. in the amount of
$386,537.08 for the 23rd Street Pavement Widening Project; and
WHEREAS, during the course of the project Change Order No. 1 is required
in the amount of$46,223.17 as described in Exhibit "A" attached hereto;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be, and he is hereby authorized, to execute a Change Order No.
1 in the amount of$46,223.17. The project, as stated above, be and the same is herein
accepted and the City Manager be and he is hereby authorized to make final payment in
the amount of$46,330.67 to be paid to Excavators & Constructors, Inc.
PASSED BY THE CITY COUNCIL of the City of Beaumont on this the
day of ��l�e� , 1997.
a
-Mayor-
CITY OF BEAUMONT
DATE: SEPTEMBER 2,1997
PROJECT: 23RD STREET PAVEMENT WIDENING
OWNER: CITY OF BEAUMONT
CONTRACTOR: EXCAVATORS&CONSTRUCTORS,INC
CHANGE ORDER NO.1
THE FOLLOWING CHANGES IN THE PLANS AND10R SPECIFICATIONS ARE HEREBY MADE:
1. 638 LF,3"conduit schedule 40(PVC)was added to the contract at a unit cost of$6.12/1-F.
638 LF X$6.12=$3,904.56
2. Adjust the estimated quantities to reflect quantities actually used in completing project.
ORIGINAL CONTRACT AMOUNT: $ 386,537.08
NET FROM PREVIOUS CHANGE ORDERS: $ 386,537.08
TOTAL AMOUNT OF THIS CHANGE ORDER: $ 46,223.17
PERCENT OF THIS CHANGE ORDER: 11.95%
TOTAL PERCENT CHANGE TO DATE: 11.95%
NEW CONTRACT AMOUNT: $ 432,760.25
CONTRACT TIMES IS NOT AFFECTED BY THIS ORDER"
AC EPTE Y:
CONTR T
APPROVED BY:
o�liJ -P
Jam, RIS P.COLBERT,CITY ENGINEER
TOM WARNER,DIRECTOR OF PUBLIC WORKS
RAY RILEY,CITY MANAGER
ATTESTED BY:
PATRICE FOGARTY,CITY CLERK
1