WHEREAS, on December 17, 1996, the City Council of the City of
Beaumont, Texas, awarded a contract to W. B. Construction, Inc. in the amount of
$721,436.45 for the Royal Street Drainage Project -- Phase I; and
WHEREAS, during the course of the project Change Order No. 1 is required
in the amount of$102,695.84 as described in Exhibit "A" attached hereto;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be, and he is hereby authorized, to execute a Change Order No.
1 in the amount of$102,695.84.
PASSED BY THE CITY COUNCIL of the City of Beaumont on this the
->?I� day of 2� �� , 1997.
-Mayor-
CITY OF BEAUNIONT
DATE: JULY 9,1997
PROJECT: ROYAL STREET DRAINAGE-PHASE I
O%'NER: CITY OF BEAUMONT
CONTRACTOR: W.B.CONSTRUCTION,INC.
CHANGE ORDER NO.I
THE FOLLOWING IS A SUNLNIARY OF MODIFICATIONS WHICH AFFECT CONTRACT ANIOUNT.
1. ADD 15'STORM SEWER FROM THE INTERSECTION OF IRMA AND VICTORIA TO AN EXISTING
INLET ON MLK. THE EXISTING SYSTEM WHICH DRAINS THIS INTERSECTION APPEARS TO BE
COLLAPSED. THIS WORK WOULD REPLACE THE FOUR INLETS AT THE CORNER OF IRMA AND
VICTORIA. THE COST FOR THIS MODIFICATION IS APPROXIMATELY $18,471.80. THE
FOLLOWING IS A SUMMARY OF MODIFIED QUANTITIES WHICH WILL BE ADDED TO THE
CONTRACT. SEE ATTACHED FIGURE 1.
ITEM DESCRIPTION QUANTITY C7rTf UNIT COST TOTAL
ADDED COST
104-002 REMOVE OLD SIDEWALKS 18.4 SY $6.00 $110.40
104-003 REMOVE OLD CURB 154 LF SL.00 Si54.00
162-001 BLOCK SODDING 150 SY $2.80 5420.00
247-001 FLEXIBLE BASE 56 SY S9.20 5515.20
340-001 ASPHALT CONCRETE 12 TONS $38.25 5359.00
400-001 CEMENT STABILIZED SAND 36 CY S23.00 $828.00
400-002 1 CUT AND RESTOR PAVING 32.6 SY $36.00 51.173.60
464-001 RCP(15') 266 LF S21.00 $5,586.00
465-001 INLET TYPE A(CI-5A) 4 EA $1,500.00 56,000.00
465.002 INLET TYPE I(W/MH COVER) 1 EA 51,370.00 $1,370.00
529-001 CONC.CURB(TYP A) 114 LF S3.50 S399.00
530-002 ASPHALT DRIVEWAYS 20.6 SY $25.00 5515.00
531-001 SIDEWALKS 18.4 SY $24.00 $441.60
496-002 REMOVING OLD STRUCT l EA S500.00 5500.00
TOTAL= $18.471.80
2. INSTALLATION OF A 13'SECTION OF CAST IN PLACE BOX IN LIEU OF THE PROPOSED PRE-CAST
STORM SEWER DUE TO THE CONFLICT OF A SANITARY SEWER NOT INDICATED ON THE
PLANS. THE FOLLOWING IS A COST BREAKDOWN OF THE BOX COSTS:
CAST IN PLACE BOX(CONCRETE,REBAR,AND LABOR) $5,156.00
ALUMINUM SLIT CASING(15'X10') $283.25
SUBTOTAL $5,439.25
OVERHEAD AND PROFIT(`,415) 5815.89
TOTAL CONTRACT INCREASE FOR THIS ITEM $6,255.14
CAROYALSTICHGORDOI.DOC PAGE 1 OF 4
EXHIBIT "A"
3. SHEET PILING WAS REQUIRED FOR THE EXCAVATION AND INSTALLATION OF THE BOX
BECAUSE GRANULAR SAND BACKFILL AROUND THE UTILITIES IN THE STREET WAS USED
DURING PRIOR CONSTRUCTION WHICH CAUSED THE STREET TO COLLAPSE.
MATERIAL AND LABOR FOR PILING TO SHORE AREA $3,297.00
OVERHEAD AND PROFIT(%15) 5614.55
TOTAL CONTRACT INCREASE FOR THIS ITEM 54941.55
4. ADDITIONAL CEMENT STABILIZED SAND REQUIRED TO BACKFILL AROUND CAST IN PLACE
BOXES,PRE CAST BOXES,AND 20' WATER LINE IN THE INTERSECTION OF ORANGE AND
CRAIG. THE EXISTING BACKFILL CONSISTED OF FINE SAND AROUND THE PREVIOUSLY
PLACED UTILITIES WHICH COLLAPSED INTO THE EXCAVATION.
ITEM QUANTITY CONTRACT UNIT TOTAL
PRICE
ADDITIONAL CEMENT STABILIZED 187.7 $23.00 54317.1
S&ND
TOTAL= $3317.10
5. DURING THE EXCAVATION FOR THE 5X5 BOXES BETWEEN STATION 36+08 AND 37+06.5,
FLOWABLE SAND WAS ENCOUNTERED. THE FLEXIBLE BASE MATERIAL WHICH IS CALLED
FOR IN THE PLANS WAS NOT APPROPRIATE TO SUPPORT THE WEIGHT OF THE BOXES IN THIS
AREA,THEREFORE, THE CONTRACTOR USED A BASE OF LARGE STONE IN THE AREA.
THE TOTAL INCREASE FOR THIS ITEM $797.40
6. DUE TO A CONFLICT AT THE CORNER OF AVE'A'AND BLANCHETTE WITH A 12'DIAMETER
HIGH PRESSURE GAS LINE IT IS NECESSARY TO SUBSTITUTE 10' DIAMETER PVC FOR THE
PROPOSED 18'RCP BETWEEN TWO CURB INLETS AND A MANHOLE. THE ELEVATION OF THE
GAS LINE ALSO NECESSITATED THE INSTALLATION OF TWO ADDITIONAL MANHOLES. THE
FOLLOWING IS A BREAKDOWN OF COSTS FOR THIS MODIFICATION:
DELETE PLAN QUANTITY 31 LF OF E8'RCP AT 522.50/LF S-697.50
ADD APPROXIMATELY 156 LF OF 10'PVC AT 519.50/LF $3,042.00
ADDITION OF TWO TYPE A MANHOLES AT 52,800.00/EA 55,600.00
TOTAL CONTRACT INCREASE FOR THIS ITEM $7,934.50
7. REPLACEMENT OF TWO PROPOSED SAFETY END TREATMENTS(SETS)WITH SURFACE INLETS.
THE FOLLOWING IS A BREAKDOWN OF COSTS FOR THIS MODIFICATION:
DELETE 2 SETS AT 51,200.00 1EA S-2,300.00
REPLACE WITH 2 TYPE A SURFACE INLETS AT$1,500.00 $3,000.00
TOTAL CONTRACT INCREASE FOR THIS ITEM $600.00
C:IROYALST\CHGORDO1.DOC PAGE'_OF 4
8. ADDITION OF I INLET AT THE NORTH EAST CORNER OF VICTORIA AND CRAIG TO PROVIDED
BETTER DRAINAGE AT THE INTERSECTION AND TO PROVIDE AN ADDITIONAL CLEAN OUT
POINT. THE MODIFICATION RESULTS IN AN INCREASE OF$1,833.55. THE FOLLOWING IS A
SUMMARY OF MODIFIED QUANTITIES WHICH WILL BE ADDED TO THE CONTRACT.
s
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL
ADDED COST
465.001 INLET TYPE A(CI-SA) 1 EA 51.500.00 51,500.00
104.003 REMOVE OLD CURB I I LF S1.00 511.,00
400-001 CEMENT STABILIZED SAND 7 CY $23.00 $161.00
400-002 CUT AND RESTORING 4 SY $36.00 $144.00
PAVING
529-001 CONC.CURB(iYP A) 5 LF S3.50 S17.50
TOTAL= $1,833.50
9. NECESSARY RE-ROUTING OF PREVIOUSLY UNIDENTIFIED 15' STORM SEWER FROM THE
INTERSECTION OF BLANCHETTE AND AVE "B" TO AVE "A" AND ROYAL STREET. THIS
MODIFICATION WILL REQUIRE THE INSTALLATION OF APPROXIMATELY 721 LINEAL FEET,-,F
STORM SEWER THAT WILL BE AN AVERAGE OF 10 FEET DEEP.
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL
ADDED COST
104-002 REMOVE OLD SIDEWALKS 158 SY $6.00 S948.00
104.003 REMOVE OLD CURB 20 LF $1.00 $20.00
247-001 FLEXIBLE BASE 7 SY $9.20 S64.-0
310-001 ASPHALT MATERIAL 2 GAL $2.10 $4.20
340-001 ASPHALT CONCRETE 7 TONS $38.25 5267-'5
400-001 CEMENT STABILIZED SAND 343 CY 523.00 57,889.00
400-002 CUT AND RESTORE PAVING 90 SY S36.00 $3,240.00
402-001 TRENCH PROTECTION 721 LF S2.00 51,442.00
464.001 RCP(15") 16 LF S21.00 5336.00
464.002 RCP(18") 721 LF S47.50 S34,247.50
465.004 MANHOLE TYPE 1 3 EA $2,800.00 $8,400.00
496-001 REMOVE OLD STRUCTURES 1 EA 5200.00 $200.00
529-001 CONC.CURB(TYP A) 20 LF $3.50 $70.00
530-002 ASPHALT DRIVEWAYS 14 SY S29.00 $406.00
TOTAL= $57,534.85
THE TOTAL AINIOUNT OF CHANGE ORDER(SUNI OF ALL ITEMS LISTED ABOVE): S102,695.84
CAROYAL.STCHGORD0I.DOC PAGE 3 OF 4
THE FOLLO"ING IS A DESCRIPTION OF MODIFICATIONS WHICH AFFECT CONTRACT TIME.
1. THE WORK ASSOCIATED WITH THE REROUTING OF STORM WATER ON BLANCHETTE AND
AVENUE-A-,ITEM 9,WILL RESULT IN A DELAY OF THE PROJECT APPROXIMATELY 21 DAYS.
SUMMARY OF CHANGE ORDER COST AND TIME CHANGES
ORIGINAL CONTRACT AMOUNT: $721,436.45
NET FROM PREVIOUS CHANGE ORDERS: S-0-
TOTAL AMOUNT OF THIS CHANGE ORDER: $102,695.84
PERCENT OF THIS CHANGE ORDER: 14.23°
TOTAL PERCENT CHANGE TO DATE: 14.23%
NEW CONTRACT AMOUNT: $824,132.29
ORIGINAL CONTRACT TIME(DAYS): 325
TIME CHANGES FOR PREVIOUS CHANGE ORDERS(DAYS): -0-
TIME CHANGES FOR THIS CHANGE ORDER(DAYS): 21
NEW CONTRACT TIME(DAYS) 346
ACCEPTED BY:
CONTRACTOR(W.B.CONSTRUCTION,INC.)
APPROVED BY:
IORIS P.COLBERT,CITY ENGINEER
TOM WARNER,DIRECTOR OF PUBLIC WORKS
RAY A.RILEY,CITY MANAGER
ATTESTED BY:
PATRICE FOGARTY,CITY CLERK
CAROYALST\CHGORDOI.DOC PAGE 4 OF 4