Loading...
HomeMy WebLinkAboutRES 98-108 RESOLUTION NO. WHEREAS, on December 18, 1996, the City Council of the City of Beaumont, Texas, awarded a contract to W. B. Construction, Inc., in the amount of $721,436.45 for the construction of the Royal Street Drainage Project - Phase 1; and WHEREAS, during the course of the project, Change Order No. 1 was approved by Council on July 22, 1997 for$102,695.84. Change Order No.2 in the amount of $747.50 did not require Council's approval, WHEREAS, Change Order No. 3 is requested in the amount of $22,683.10 to adjust the estimated quantities to reflect the final quantities actually used in the contract thus increasing the final contract amount to $847,562.89 as described in Exhibit "A" attached hereto; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the City Manager be, and he is hereby authorized, to execute Change Order No. 3 in the amount of $22,683.10. The project, as stated above, be and the same is herein accepted and the City Manager be and he is hereby authorized to make final payment of the retainage in the amount of $84,316.70 to be paid to W. B. Construction., Inc. PASSED BY THE CITY COUNCIL of the City of Beaumont on this the J�,-,/z day of Mayor - CITY OF BEAUMONT DATE: APRIL 24, 1998 PROJECT: ROYAL STREET DRAINAGE-PHASE I OWNER: CITY OF BEAUMONT CONTRACTOR: W. B. CONSTRUCTION, INC. CHANGE ORDER NO.3 THE FOLLOWING IS A DESCRIPTION OF MODIFICATIONS WHICH AFFECT CONTRACT AMOUNT. 1. ADJUST THE ESTIMATED QUANTITIES TO REFLECT THE FINAL QUANTITIES ACTUALLY USED. THE COST FOR THIS MODIFICATION IS$22,683.10. SUMMARY OF CHANGE ORDER COST AND TIME CHANGES: ORIGINAL CONTRACT AMOUNT: $721,436.45 NET FROM PREVIOUS CHANGE ORDERS: $103,443.34 TOTAL AMOUNT OF THIS CHANGE ORDER: $ 22,683.10 PERCENT OF THIS CHANGE ORDER: 3.14% TOTAL PERCENT CHANGE TO DATE: 17.48% NEW CONTRACT AMOUNT: $847,562.89 ORIGINAL CONTRACT TIME(DAYS): 325 TIME CHANGES FOR PREVIOUS CHANGE ORDERS (DAYS): 51 TIME CHANGES FOR THIS CHANGE ORDER(DAYS): 0 NEW CONTRACT TIME(DAYS): 376 ACCEPTED BY: CONTRACTOR(W. B.CONSTRUCTION,INC.) APPROVED BY: JORIS P.COLBERT, CITY ENGINEER TOM WARNER, DIRECTOR OF PUBILC WORKS RAY A. RILEY,CITY MANAGER ATTESTED BY: PAT RICE FOGARTY,CITY CLERK EXHIBIT "A"