HomeMy WebLinkAboutRES 98-26 RESOLUTION NO.
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
THAT the five-year Capital Program for Fiscal Year 1998 through Fiscal Year 2002 is
amended to reflect the addition of the Chaison Street Extension for the estimated amount
of$200,000 as described in Exhibit "A" attached hereto; and the preparation of plan and
specifications for the project is hereby authorized.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 3�_ day of
, 1998.
,
- MAYOR -
EXHIBIT 2
CITY OF BEAUMONT
PROJECT: SOUTH PARK DRAINAGE PROJECT, PHASE I
ESTIMATE FOR PAVING TO HARRIOT
ITEM I UNIT , EST. I UNIT
j NO DESCRIPTION ' MEASURE QUAN. PRICE TOTAL
10» jREMOVE OLD CONCRETE(PAV.) S.Y. 1C0i S3.731 5373.201
104 1 REMOVE OLD CONCRETE(MISC.) S.Y. 1001 S4.921 5492.00
110 !EXCAVATION I C.Y. 9801 S6.921 $6,785.52
132 I EMBANKMENT(D.C.)(i`!."8) I C.Y. I 1301 $5.051 S656.70
150 1BLADING I HR. 1 151 S30.001 5450.00
152 (BLOCK SODDING FOR EROSION CONT.(ST.AUG) 1 S.Y. 1 1221 $4.071 5496.30
158 !SPECIALIZED EXCAVATION WORK I HR. ( 151 $84.001 51,260.001
260 (LIME TREATMENT(81(7 16) 1 S.Y. 1 15901 55.041 $8.013.60
276 ICEM.STAB.BS.(D.C.)(GR 3)(CL 5)(8 IN.) 1 S.Y. 1 7441 $15.26 $11,350'.42
315 1 EMULSIFIED ASPHALT SEAL(PRIME COAT)(AE•P) I GAL. 1 1861 52.701 5502.201
340 1ASPH.CONC.(TY.D) I TON 801 $66.001 $5.280.00
360 1 CONC.PAVEMENT(CLASS A CONC.)(7 IN.) 1 S.Y. 1 18301 $29.881 554,680.40
400 1STRUCTURAL EXCAVATION 1 C.Y. 1 8901 S2.401 $2,136.00
400 ICEM.STAB.BACKFILL 1 C.Y. 1 3931 $23.27 $9,144.32
402 1TRENCH EXCAVATION PROT.(PIPE&BOX) 1 L.F. 1 5501 $0.01 56.601
402 (TRENCH EXCAVATION PROT.(INLETS&MANHOLES) I S.F. 1001 $0.011 S1.20
460 1CORRUGATED ALUMINIZED STEEL PIPE(18 IN.) 1 L.F. 1 1681 $26.811 $4,503.74
460 1CORRUGATED ALUMINIZED STEEL PIPE(42 IN.) 1 L.F. 1 5501 $56.60 531,132.20
465 1INLET(COMPL.)(TY.A) 1 EA. 1 41 $1,584.22 56,336.86
465 1MANHOLE(COMPL.)(TY.A) i EA. 1 21 $2,811.35 $5,622.70
496 REMOVE OLD STR.(PIPE) I L.F. 1501 $2.591 5388.801
500 1MOBILIZATION 1 L.S. 1 11 $18,000.001 S18.000.00
502 1SARCD.,SIGN AND TRAFFIC HANDLING 1 MO. 1 41 $1,186.80 $4,747.20
529 1CONCRETE CURB 1 L.F. 1 1151 53.42 5393.30;
530 1CONC.DRIVEWAY(4 IN.) I S.Y. 1 700; 530.001 521,400.001
531 jCONC.SIDEWALKS(4 IN.) j S.Y. 1 601 531.201 $1,872.00'i
,
5000 1 MISC.WATER AND SEWER WORK 1 EA. 1 11 $4,200.001 54,200.00!
TOTAL $1 99,831.32
EXHIBIT "A"