HomeMy WebLinkAboutRES 99-297 RESOLUTION NO. -22-2.�2
WHEREAS, on February 16, 1999, the City Council of the City of Beaumont,
Texas, awarded a contract to BoMac Contractors, Inc. in the amount of $1,046,504.63 for
improvements to the Beaumont Fire Training Center; and
WHEREAS, during the course of the project, Change Order No. 1 was
approved by Council on July 27, 1999; and
WHEREAS, Change Order No. 2 was approved by Council on August 10,
1999;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be, and he is hereby authorized, to execute Change Order No. 3
in the amount of $27,452 for added work as shown on attached Exhibit "A"
PASSED BY THE CITY COUNCIL of the City of Beaumont on this the
day of [I/ 1999.
- Mayor -
CITY OF BEAUMONT
CHANGE ORDER NO. 3
DATE: September 27, 1999
PROJECT: IMPROVEMENTS TO THE BEAUMONT FIRE TRAINING CENTER
OWNER: CITY OF BEAUMONT
CONTRACTOR: BOMAC CONTRACTORS, INC.
THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE:
Amend the scope of the project to add pay items to the contract:
11 Install 160 LF 18" Corrugated Plastic Pipe, 12 LF 36" Reinforced Concrete Pipe and 1500 CY
Select Fill to facilitate drainage between Project Area no. 4 and the south levee of the Drafting
Pond. Estimated cost: $24,348.
2) Fill the base of the new Fire Water Pump with non-shrink grout to prevent vibration damage to
the pump base and the floor of the pump pit during pump operation. Estimated cost: $2,467.
3) Revise 4" pipe casings at Fire Extinguisher Project Area to facilitate easier installation of
process piping. Estimated cost: $449.
4) Add welding to 36" Pipe Nozzle at the north sump to improve strength and liquid holding
integrity. Estimated cost: $188.
ORIGINAL CONTRACT AMOUNT: $1,046,504.63
NET FROM PREVIOUS CHANGE ORDERS: $ 38,825.00
TOTAL AMOUNT OF THIS CHANGE ORDER: $ 27.452.00
PERCENT CHANGE OF THIS CHANGE ORDER: 2.62%
TOTAL PERCENT CHANGE TO DATE: 6.33%
NEW CONTRACT AMOUNT: $1,112,781.63
CONTRACT TIME IS NOT AFFECTED BY THIS CHANGE ORDER.
ACCEPTED BY:
CONTRACTOR
APPROVED BY:
JORIS P. COLBERT, CITY ENGINEER
TOM WARNER, DIRECTOR OF PUBLIC WORKS
STEPHEN J. BONCZEK, CITY MANAGER
ATTESTED BY:
BARBARA LIMING, CITY CLERK
EXHIBIT "A"