WHEREAS, on November 3, 1998, the City Council of the City of Beaumont,
Texas, awarded a contract to Excavators & Constructors, Inc. in the amount of
$159,553.05 for the Chaison Street Pavement Widening Project; and
WHEREAS, during the course of the project Change Order No. 1 is required
in the amount of ($5,177.56) to adjust the estimated quantities to reflect the quantities
actually used during the performance of the project;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be, and he is hereby authorized, to execute Change Order No. 1
decreasing the contract in the amount of$5,177.56. The project, as stated above, be and
the same is herein accepted and the City Manager be and he is hereby authorized to make
final payment in the amount of $71,511.35 to be paid to Excavators & Constructors, Inc.