HomeMy WebLinkAboutRES 01-072 RESOLUTION NO. 01-072
WHEREAS, on March 7, 2001, the City Council of the City of Beaumont, Texas,
awarded a contract to Brystar Contracting, Inc.for construction of Folsom Drive Pavement
Extension from Dowlen Road to Major Drive in the amount of$2,389,270.90; and,
WHEREAS, Change Order No. 1 in the amount of$26,637.43 is required to adjust
the estimated quantities used during performance of the project, increasing the contract
to $2,415,908.33;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be, and he is hereby authorized, to execute Change Order No.
1 in the amount of$26,637.43 to adjust the estimated quantities used during performance
of the project, increasing the contract to $2,415,908.33. The project, as stated above, be
and the same is herein accepted and the City Manager be and he is hereby authorized to
make final payment in the amount of$158,745.86 to be paid to Brystar Contracting, Inc.
PASSED BY THE CITY COUNCIL of the City of Beaumont on this the 20th day of
March, 2001.