HomeMy WebLinkAboutRES 18-123RESOLUTION NO. 18-123 I WHEREAS, on April 25, 2017, the City Council of the City of Beaumont, Texas, passed Resolution No. 17-083 awarding a contract in the amount of $15,984,397.88 to Allco, L.L.C., of Beaumont, Texas, for the Washington Boulevard Pavement Widening Phase 11 (Corporate Drive to Amarillo Street) Project; and, WHEREAS, on August 3, 2017, the City Manager executed Change Order No. 1, in the amount of $9,920.00, to adjust the estimated quantities to reflect the actual quantities used in the completion of the project, thereby increasing the contract amount to $15,994,317.88; and, WHEREAS, on February 6, 2018, the City Council of the City of Beaumont, Texas, passed Resolution No. 18-032 authorizing' the City Manager to execute Change Order No. 2, in the amount of $103,893.00, to accommodate design changes necessary to address unforeseen conflicts with the underground utilities and additional curb and driveway improvements required on Executive Boulevard and Corporate Drive, thereby increasing the contract amount to $16,098,210.88; and, WHEREAS, on May 14,2018, the City Manager executed Change Order No. 3, in the amount of $7,714.55, to adjust the estimated quantities to reflect the actual quantities used in the completion of the project, thereby increasing the contract amount to $16,105,925.43; and, WHEREAS, Change Order No. 4, in the amount of $16,032.91, is necessary to adjust the pipe quantity and size which was not allotted for in the original design and the addition of fourteen (14) calendar days, thereby increasing the contract amount to $16,121,958.34; NOW, THEREFORE, BE IT RESOLVED BY THE ,CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the statements and findings set out in the preamble to this resolution are hereby, in all things, approved and adopted; and, THAT the City Manager be and he is hereby authorized to execute Change Order No. 4 for additional work described above, thereby increasing the contract amount by $16,032.91 for a total contract amount of $16,121,958.34 for the Washington Boulevard Pavement Widening Phase 11 (Corporate Drive to Amarillo Street) Project. The meeting at which this resolution was approved was in all things conducted in strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter 551.2 PASSED BY THE CITY COUNCIL of the City of Beaumont this the 5th day of June, 2018. *Ukg- I � 4w,11 - V - ft(or Bd'cky-Ames - I