Loading...
HomeMy WebLinkAboutRES 94-180 RESOLUTION NO. WHEREAS, on February 8, 1994, City Council awarded a Contract to Affolter Contracting, Inc.for Remediation and Drainage Improvements for the Fire Training Center in the amount of $980,681.70; and, WHEREAS, Change Order No. 1 changed the scope of the project, but did not increase the total cost nor the time of the Contract; and, WHEREAS, Change Order No. 2 is being requested to increase the contract amount by $20,892.90 for replacing 310.6 tons of stabilized sand at $16.00 per ton for a credit of $4,969.60) with 206.9 cubic yards of concrete at $125.00 per cubic yard (at a cost of $25,862.50) increasing the contract amount to $1,001,574.60; and, NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the City Manager be and he is hereby authorized to execute Change Order No. 2 as stated above with Affolter Contracting, Inc. PASSED BY THE CITY COUNCIL of the City of Beaumont this the% day of Q, 1994. - Mayor -