Loading...
HomeMy WebLinkAboutRES 03-128 RESOLUTION NO. 03-128 WHEREAS, on November 26, 2002, the City Council of the City of Beaumont, Texas, awarded a contract to Brystar Contracting, Inc., Beaumont, Texas, in the amount of $934,800.50 for the Proposed 20" Water Line Relocation at Major Drive (FM364) Project; and, WHEREAS, Change Order No. 1 in the amount of$15,314.15 is required to install 0.32 tons of ductile iron fittings, install one (1)fire hydrant assembly, install 652.41 tons of cement stabilized sand backfill, remove and replace 90 linear feet of wood fence, install 144 linear feet of 2-inch water service lines, and 135 linear feet of 4-inch schedule 40 steel casing thereby increasing the contract amount to $950,114.65; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the City Manager be, and he is hereby authorized, to execute Change Order No. 1 in the amount of$15,314.15 to install 0.32 tons of ductile iron fittings, install one (1)fire hydrant assembly, install 652.41 tons of cement stabilized sand backfill, remove and replace 90 linear feet of wood fence, install 144 linear feet of 2-inch water service lines, and 135 linear feet of 4-inch schedule 40 steel casing thereby increasing the contract amount to $950,114.65. PASSED BY THE CITY COUNCIL of the City of Beaumont this the 17th day of June, 2003. - May Evelyn M. Lord -